Contract
No: HK/2011/07 Wanchai Development Phase
II and Sampling, Field Measurement and
Testing Works
(Stage 2) Environmental Permit no. EP-356/2009, Further Evironmental permit nos.
fep-02/356/2009, FEP-03/356/2009, Fep-04/356/2009 and Fep-05/356/2009 Monthly Environmental Monitoring & Audit Report
- November 2012 -
|
CLIENTS: |
|
Civil Engineering and Development Department and Highways Department |
Lam Geotechnics Limited 11/F Centre Point Wanchai, H.K. Telephone:
(852) 2882-3939 Facsimile:
(852) 2882-3331 E-mail:
info@lamenviro.com Website:
http://www.lamenviro.com |
|
|
|
|
|
Certified by: |
|
Raymond
Dai Environmental
Team Leader |
|
DATE: |
|
13 December 2012 |
2.2 Scope of the Project and Site Description
2.3 Division of the Project Responsibility
2.4 Project Organization and Contact Personnel
3. Status of Regulatory Compliance
3.1 Status of Environmental Licensing and Permitting under
the Project
5.2 Real-time Noise Monitoring
6.2 Real-time noise Monitoring
6.5 Review of the Reasons for and the Implications of
Non-compliance
6.6 Summary of action taken in the event of and follow-up
on non-compliance
7. Cumulative Construction Impact due to the Concurrent
Projects
9. Complaints, Notification of Summons and Prosecution
lIST OF TABLES
Table I Summary of Water Quality Monitoring Exceedances in
Reporting Month
Table II Summary of Enhanced Dissolved Oxygen Monitoring
Exceedances in Reporting Month
Table 2.1 Schedule 2 Designated Projects under this Project
Table 2.2 Details of Individual Contracts under the Project
Table 2.3 Contact Details of Key Personnel
Table 3.4 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2009/01
Table 3.5 Summary of submission status under FEP-02/356/2009
Condition
Table 3.6 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2009/02
Table 3.7 Summary of submission status under FEP-03/356/2009
Condition
Table 3.8 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/15
Table 3.9 Summary of submission status under FEP-04/356/2009
Condition
Table 3.10 Cumulative Summary of Valid Licences and Permits under
Contract no. HK/2010/06
Table 3.11 Summary of submission status under EP-356/2009 and
FEP-05/356/2009 Condition
Table 3.12 Cumulative Summary of Valid Licences and Permits under
Contract no. HY/2009/19
Table 4.1 Noise Monitoring Station
Table 4.2 Real Time Noise Monitoring Station
Table 4.3 Air Monitoring Station
Table 4.4 Marine Water Quality Stations for Water Quality
Monitoring
Table 4.5 Marine Water Quality Monitoring Frequency and
Parameters
Table 4.6 Marine Water Quality Stations for Enhanced Water Quality
Monitoring
Table 4.7 Marine Water Quality Stations for Additional DO
Monitoring
Table 5.2 Noise Monitoring Station for Contract nos. HK/2009/01,
HK/2009/02 and HK/2010/06
Table 5.3 Noise Monitoring Station for Contract no. HY/2009/15
Table 5.4 Noise Monitoring Station for Contract no. HY/2009/19
Table 5.5 Real Time Noise Monitoring Station for Contract no.
HY/2009/19
Table 5.8 Air Monitoring Station for Contract no. HK/2009/02
Table 5.9 Air Monitoring Station for Contract no. HY/2009/15
Table 5.10 Air
Monitoring Stations for Contract no. HY/2009/19
Table 5.12 Water
Monitoring Stations for Contract no. HK/2009/01
Table 5.13 Water
Monitoring Stations for Contract no. HK/2009/02
Table 5.14 Water
Monitoring Stations for Contract no. HK/2010/06
Table 5.15 Water
Monitoring Stations for Contract no. HY/2009/15
Table 5.16 Water
Monitoring Stations for Contract no. HY/2009/19
Table 5.17 Summary
of Water Quality Monitoring Exceedances in Reporting Month
Table 5.18 Summary
of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month
Table 5.19 Details of Waste Disposal for Contract no. HK/2009/01
Table 5.20 Details of Waste Disposal for Contract no. HK/2009/02
Table 5.21 Details of Waste Disposal for Contract no. HY/2009/15
Table 5.22 Details of Waste Disposal for Contract no. HK/2010/06
Table 5.23 Details of Waste Disposal for Contract no. HY/2009/19
Table 8.1 Summary of Environmental Inspections for Contract no.
HK/2009/01
Table 8.2 Summary of Environmental Inspections for Contract no.
HK/2009/02
Table 8.3 Summary of Environmental Inspections for Contract no.
HY/2009/15
Table 8.4 Summary of Environmental Inspections for Contract no.
HK/2010/06
Table 8.5 Summary of Environmental Inspections for Contract no.
HY/2009/19
Table 9.1 Cumulative Statistics on Complaints
Table 9.2 Cumulative Statistics on Successful Prosecutions
Table 10.1 Construction Activities and Recommended Mitigation
Measures in Coming Reporting Month
lIST
OF FIGUREs
Figure 2.2 Project Organization Chart
Figure 2.3 Locations of Environmental Monitoring Stations
lIST
OF APPENDIces
Appendix 3.1 Environmental Mitigation Implementation Schedule
Appendix 4.1 Action and Limit Level
Appendix 4.2 Copies of Calibration Certificates
Appendix 5.1 Monitoring Schedule for Reporting Month and Coming month
Appendix 5.2 Noise Monitoring Results and Graphical Presentations
Appendix 5.3 Air Quality Monitoring Results and Graphical Presentations
Appendix 5.4 Water Quality Monitoring Results and Graphical Presentations
Appendix 5.4a Additional Dissolved Oxygen Monitoring Results
Appendix 5.5 Real-time Noise Monitoring Results and Graphical Presentations
Appendix 6.1 Event Action Plans
Appendix 6.2 Summary for Notification of Exceedance
Appendix 8.1 Construction Programme of Individual Contracts
Construction Activities for the Reported Period
Marine Works (at Wan Chai)
¡P
Rockfilling for HKCEC3E (East of HKCEC) between CH290 and CH385
¡P
Grouting works to pipe pile at
¡P
Removal of existing seawall and rock armour at
¡P
Dredging underneath
¡P
Fabrication of 3 nos. of precast concrete caisson seawall, 1 no. precast
concrete box culvert (namely Bay 10) and 2 nos. precast discharge outfall in
precasting yard at
Cross-Harbour Watermains Installation (CHA & CHB) and Marine Works
(at TST)
¡P
Rockfilling and rock protection to cross-harbour watermains
¡P
Thrust block construction for A18B18
¡P
Connection work between land pipeline and marine pipeline
¡P
Reinstatement works for the TST landfall
Fresh Watermains, Cooling Watermains and Salt Watermains (On Land)
¡P
Mainlaying works at Zone B1-5A, B2-1, B3-1, A1-1, A1-2, A1-4, A1-2A
& A1-3A, A2-3D, A3-2A, A3-4B, A3-3C, C1-6 and run-out of Renaissance Hotel
¡P
Mainlaying works at TTA Zone A2-3D and A1-4
¡P
Pipe laying works at heading No. H1 and Zone A3-4B
¡P
Mainlaying works at Zone A3-3C
¡P
Mainlaying and chamber construction works at the traffic island near
junction of
¡P
Mainlaying works at
¡P
Final cleaning, CCTV inspection and pressure test for the 9 nos. cooling
watermains
E&M
¡P
Electrical works in cooling water pumping stations P5
¡P
Major cabling works from existing LV Switch-board Room to Cooling Water
Pumping Station P5
¡P
Power energization to L.V. switchboard for cooling water pumping
stations P5
¡P
Full commissioning for Cooling Water Pumping Stations P1
¡P
Repairing of door hinges in the New Public Toilet..
¡P
Modification work of PTI at
¡P
Modification work of bus station at
¡P
Pre-inspection for P9 (SHK) Pumping Station.Reinstatement at
¡P
Cooling mains installation at west of Gate 1 inside ex-pet garden
¡P
Cooling main remedial works for the bending pipes
¡P
Installation of optic fiber and power cable
¡P
E&M works and ABWFs installation at WSD Salt Water Pumping Station
¡P
Concreting of boundary wall of EVA at WSD Pumping Station
¡P
Concreting of Inspection Manhole and Access Chamber of Salt Water Intake
Culvert at Bay 19B & 20
¡P
Concreting of the wall and top slab at salt water intake culvert Bay
¡P
Concreting of the blinding layer at salt water intake culvert Bay 9 -
Bay 11 at WCR1
¡P
Concreting of the wall and top slab at salt water intake culvert Bay 9
at WCR1 and steel fixing of base slab at Bay 10
¡P
Cutting the sheetpile wall at salt water intake culvert Bay 11 to
jacking pit
¡P
Concreting of wall and top slab of Bay
¡P
TZ1 and TS2 reclamation works
¡P
Formation of temporary seawall at TS2
¡P
Pile head breaking
¡P
Platform Disassembly
¡P
Bored Pile cutting
¡P
Marine bored piling
¡P
Construction works for Box Culvert T
¡P
Construction of 1500f drainage pipe
Real-time Noise
Monitoring
Air Quality Monitoring
CMA2a: from 8 and 14 November 2012 to 9 and 15 November 2012
CMA5a: from 8 November 2012 to 9 November 2012
Water Quality Monitoring
3 Nov 2012
Mid-Ebb tide
5 Nov 2012
Mid-Flood tide
6 Nov 2012
Mid-Ebb tide
Table
I Summary of Water Quality
Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring
Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
|||||||||
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|||
HK/2009/01 |
WSD19 |
0 |
0 |
2 |
1 |
0 |
1 |
0 |
0 |
3 |
2 |
0 |
1 |
|
|
C1 |
0 |
0 |
0 |
0 |
0 |
0
|
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C3 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C4e |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C4w |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
|
Monitoring finished on 27 April 2012 |
WSD20 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
HK/2009/01 & HK/2010/06 |
C2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
1 |
0 |
|
|
C5w |
0 |
0 |
1 |
1 |
0 |
1 |
0 |
0 |
0 |
1 |
1 |
0 |
|
Monitoring started on 8 Feb 2012 |
WSD21 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
1 |
1 |
|
WSD9 |
0 |
0 |
1 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
||
|
WSD17
|
0 |
0 |
4 |
2 |
0 |
3 |
0 |
0 |
2 |
0 |
0 |
1 |
|
HY/2009/15 |
C7 |
1 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HY/2009/19 Monitoring started on 28 Jan 2012 |
C8 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
|
C9 |
0 |
0 |
3 |
4 |
2 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
||
Total |
3 |
0 |
12 |
10 |
3 |
6 |
0 |
0 |
9 |
6 |
4 |
3 |
||
Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.
- WSD9 and WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.
-
4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8 and C9
were completed on 6 Feb 2012.
-
C8 and C9 were implemented with respect to HY/2009/19 from 28 Jan 2012.
-
WSD7 and WSD20 water quality monitoring were temporarily suspended from
27 Apr 2012.
Table
II Summary of Enhanced Dissolved
Oxygen Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
|
LL |
|
LL |
||
HY/2009/15 |
C6 |
0 |
0 |
1 |
0 |
C7 |
0 |
1 |
1 |
0 |
|
Ex-WPCWA SW |
0 |
6 |
1 |
1 |
|
Ex-WPCWA SE |
4 |
5 |
5 |
3 |
|
Total |
4 |
12 |
8 |
4 |
Complaints, Notifications of Summons and Successful Prosecutions
Site Inspections and Audit
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
Marine Works
¡P
Fabrication of precast concrete caisson seawalls, precast box culvert
(Bay 10) and precast discharge outfall in precasting yard at
¡P
Dredging works for Type 2 sediment underneath
¡P
Dredging works between CH290 and CH370 at east of HKCEC near Wan Chai
west ferry pier would be commenced after completion of removal of high spot of
Grade 75 rock fill along the submarine pipeline of cross-harbour watermains.
¡P
Excavation work and tie back system for construction of pipe pile wall
near expo drive East
¡P
Removal of seawall and rock armour at
¡P
Rockfilling at east of HKCEC near
¡P
Trust block construction at TST landfall
¡P
Rockfilling and rock armour protection works to cross-harbour watermains
¡P
Reinstatement works at TST seashore including removal of silt screen
¡P
Fresh water flushing, final cleaning and sterilizatioin for
cross-harbour watermains CHA, CHB, CHE & CHF
¡P
Installation of Impressed Current Cathodic Protection (ICCP) system to
CHA and CHB
Fresh Watermains, Cooling
Watermains and Salt Watermains (On Land)
¡P
Works would be continued at Zone B1-5A, B2-1, B3-1, A1-1, A1-2, A2-2,
A1-4(CHWM), A2-3D, A3-2A, A3-4B, A3-3C, run-out of Renaissance Hotel and C1-6
¡P
Mainlaying works at Zone C1-6
¡P
Reinstatement works at Zone B1-5A and B2-1
¡P
Mainlaying works at Zone B3-1
¡P
Mainlaying works at
¡P
Mainlaying works and grouting works at jacking pit in Zone A1-2A &
A1-3A of
¡P
Mainlaying works at traffic island near junction between
¡P
Pipe laying works for Heading no. H1 would be continued .The remaining
pipe works at Zone A3-2A
¡P
Mainlaying works at Zone A3-4B would be continued and the works at Zone
A3-4A & A3-5A would be subsequently commenced concurrently after the Zone
A3-4B had been completed reinstated and reopened to public.
¡P
Pressure test for the 1 no. cooling watermains (AF)
E&M Works
¡P
Electrical works in Cooling Water Pumping Stations P5
¡P
Power supply to cooling water pumping station P5 from L.V. switchboard
¡P
Initial commissioning for Cooling Water Pumping Stations P5
¡P
Power energization for Cooling Water Pumping Stations P5
¡P
Full commissioning for Cooling Water Pumping Stations P3, P4 & P5
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
¡P
Complete rectification works of cooling mains
and pressure test.
¡P
Continue 800MS pipe installation inside
¡P
Continue entrance area works at WSD Pumping
Station
¡P
Continue the finishing and E&M works of
WSD Salt Water Pumping Station.
¡P
Continue construction of Bay 1b ¡V 2 Salt
water intake culverts at WCR1 area.
¡P
Complete salt water intake
¡P
Continue salt water intake culvert at
transition bays inside jacking pit.
¡P
Continue remaining drainage works and reinstatement
works along
¡P
Complete Outfall Pipe B connection inside
outfall seaside cofferdam and Dye Tests
¡P
Continue construction of 1800 connection of Box
Culvert N1, Bay 4 & Bay 5 and
FRP installation at WCR1 area.
¡P
Commence concreting works for the Observation
Deck Level at the New Ferry Pier.
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
¡P
Formation of temporary seawall at TS2
¡P
TZ1 and TS2 reclamation works
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
¡P
Pile head breaking
¡P
Platform Disassembly
¡P
Dredging
¡P
Bored Pile cutting
Contract no. HY/2009/19- Wan Chai Bypass Tunnel
(North Point Section) and Island Eastern Corridor Link
¡P
Construction works for Box Culvert T
¡P
Marine Piling
¡P
Construction of 1500f drainage pipe
1.1.1.
Lam Geotechnics Limited (LGL) has been appointed to
work as the Environmental Team (ET) under Environmental Permit no. EP-356/2009
and Further Environmental permit nos. FEP-02/356/2009, FEP-03/356/2009,
FEP-04/356/2009 and FEP-05/356/2009 to implement the Environmental Monitoring
and Audit (EM&A) programme as stipulated in the EM&A Manual of the
approved Environmental Impact Assessment (EIA) Report for Wan Chai Development
phase II and Central-Wan Chai Bypass (Register No.: AEIAR-125/2008) and in the
EM&A Manual of the approved EIA Report for Central-Wan Chai Bypass and
Island Eastern Corridor Link (Register No. AEIAR-014/2001).
1.1.2.
This report presents the environmental monitoring
and auditing work carried out in accordance to the Section 10.3 of EM&A Manual
and ¡§Environmental Monitoring and Audit Requirements¡¨ under Particular
Specification Section 27.
1.1.3.
This report documents the finding of EM&A works
for Environmental Permit no. EP-356/2009, Further Environmental Permit no.
FEP-02/356/2009, FEP-03/356/2009, FEP-04/356/2009 and FEP-05/356/2009 and during
the period of October to November. The cut-off date of reporting is at 27th
of each reporting month.
Section
1 Introduction ¡V
details the scope and structure of the report.
Section
2 Project
Background ¡V summarizes background and scope of the
project, site description, project organization and contact details of key
personnel during the reporting period.
Section
3 Status of Regulatory Compliance ¡V
summarizes the status of valid Environmental Permits / Licenses during the
reporting period.
Section
4 Monitoring
Requirements ¡V summarizes all monitoring parameters,
monitoring methodology and equipment, monitoring locations, monitoring
frequency, criteria and respective event and action plan and monitoring
programmes.
Section
5 Monitoring
Results ¡V summarizes the monitoring results
obtained in the reporting period.
Section
6 Compliance
Audit ¡V summarizes the auditing of monitoring
results, all exceedances environmental parameters.
Section
7 Cumulative Construction Impact due to the
Concurrent Projects ¡V summarizes the relevant cumulative construction
impact due to the concurrent activities of the concurrent Projects.
Section
8 Site Inspection ¡V
summarizes the findings of weekly site inspections undertaken within the
reporting period, with a review
of any relevant
follow-up actions
within the reporting period.
Section
9 Complaints, Notification of summons and Prosecution
¡V summarizes the cumulative statistics on complaints, notification
of summons and prosecution
Section
10 Conclusion
2.1.1.
¡§Wan Chai Development phase II and Central-Wan Chai
Bypass¡¨ and ¡§Central-Wan Chai Bypass and Island Eastern Corridor Link¡¨
(hereafter called ¡§the Project¡¨) are Designed Project (DP) under the
Environmental Impact Assessment Ordinance (Cap. 499) (EIAO). The Environmental
Impact Assessment (EIA) Reports for Central-Wan Chai Bypass and
2.1.2.
The key purpose of Wan Chai Development Phase II
(WDII) is to provide land at Wan Chai North and North Point for construction of
the Central-Wan Chai Bypass and Island Eastern Corridor Link (CWB). Land formed
under the project will be developed as a world-class waterfront promenade
joining that at the new Central waterfront for public enjoyment.
2.1.3.
There is a compelling and present need for the CWB
to provide relief to the very congested
2.2.1.
The Project is located mainly in Wan Chai North,
2.2.2.
The study area encompasses existing developments
along the Wan Chai,
2.2.3.
The scope of the Project
comprises:
¡P
Land formation
for key transport infrastructure and facilities, including the Trunk Road (i.e. CWB) and the associated
slip roads for connection to the Trunk Road and for through traffic from Central to
Wan Chai and Causeway Bay. The land formed for the above transport infrastructure
will provide opportunities for the development of an attractive waterfront
promenade for the enjoyment of the public
¡P
Reprovisioning /
protection of the existing facilities and structures affected by the land
formation works mentioned above
¡P
Extension,
modification, reprovisioning or protection of existing storm water drainage
outfalls, sewerage outfalls and watermains affected by the revised land use and
land formation works mentioned above
¡P
Upgrading of
hinterland storm water drainage system and sewerage system, which would be
rendered insufficient by the land formation works mentioned above
¡P
Provision of the
ground level roads, flyovers, footbridges, necessary transport facilities and
the associated utility services
¡P
Construction of
the new waterfront promenade, landscape works and the associated utility
services
¡P
The Trunk Road
(i.e. CWB) within the study area and the associated slip roads for connection
to the Trunk Road.
2.2.4.
The project also contains various Schedule 2 DPs
that, under the EIAO, require Environmental Permits (EPs) to be granted by the
DEP before they may be either constructed or operated. Table 2.1
summarises the five individual DPs under this Project. Figure 2.1 shows the
locations of these Schedule 2 DPs.
Table 2.1 Schedule
2 Designated Projects under this Project
Item |
Designated Project |
EIAO Reference |
Reason for inclusion |
DP1 |
Central-Wanchai Bypass (CWB) including its road tunnel and slip roads |
Schedule 2, Part I, A.1 and A.7 |
Trunk road and road tunnel more than 800 m in length |
DP2 |
Road P2 and other roads which are classified as primary/district
distributor roads |
Schedule 2, Part I, A.1 |
Primary / district distributor roads |
DP3 |
Reclamation works including associated dredging works |
Schedule 2, Part I, C.1 and C.12 |
Reclamation more than 5 ha in size and a dredging operation less than
100 m from a seawater intake point |
DP5 |
Wan Chai East Sewage Outfall |
Schedule 2, Part I, F.5 and F.6 |
Submarine sewage pipelines with a total diameter more than 1,200 mm
and include a submarine sewage outfall |
DP6 |
Dredging for the Cross-harbour Water Mains from Wan Chai to Tsim Sha
Tsui |
Schedule 2, Part I, C.12 |
A dredging operation less than 100 m from a seawater intake point |
2.3.1.
Due to the multi-contract nature of the Project,
there are a number of contracts sub-dividing the whole works area into
different work areas to be commenced. Contractors of individual contracts will
be required by the EP holder to apply Further Environmental Permits (FEP) such
that the impact monitoring stations are sub-divided accordingly to facilitate
the implementation of EM&A programme and to streamline the EM&A reporting
for individual FEP holders correspondingly.
2.3.2.
The details of individual contracts are summarized
in Table 2.2.
Table 2.2 Details
of Individual Contracts under the Project
Contract No. |
Contract Title |
Associated DP(s) |
Construction
Commencement Date |
HK/2009/01 |
Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at |
DP3, DP6 |
23 July 2010 |
DP1, DP2 |
25 August 2011 |
||
HK/2009/02 |
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai
East |
DP3, DP5 |
5 July 2010 |
DP1 |
26 April 2011 |
||
HY/2009/11 |
Wan Chai Development Phase II and Central ¡V Wan Chai Bypass ¡V North
Point Reclamation |
DP3 |
17 March 2010 |
HY/2009/15 |
Central-Wanchai Bypass ¡V Tunnel ( |
DP3 |
10 November 2010 |
DP1 |
13 July 2011 |
||
HK/2010/06 |
Wan Chai Development Phase II-Central-Wan Chai Bypass over MTR Tsuen
Wan Line |
DP3 |
22 March 2011 |
04/HY/2006 |
Reconstruction of Bus Terminus near |
DP1 |
September 2010 |
HY/2009/17 |
Central - Wan Chai Bypass (CWB) at FEHD Whitfield Depot - Advanced
piling works. |
DP1 |
5 October 2010 |
HY/2009/18 |
Central - Wan Chai Bypass (CWB) ¡V Central Interchange |
DP1 |
21 April 2011 |
HY/2009/19 |
Central - Wanchai Bypass Tunnel (North Point Section) and Island
Eastern Corridor Link |
DP1 |
24 March 2011 |
2.4.1.
Civil Engineering and Development Department and
Highways Department are the overall project controllers for the Wan Chai
Development Phase II and Central-Wan Chai Bypass respectively. For the
construction phase of the Project, Project Engineer, Contractor(s),
Environmental Team and Independent Environmental Checker are appointed to
manage and control environmental issues.
2.4.2.
The proposed project organization and lines of
communication with respect to environmental protection works are shown in Figure 2.2. Key
personnel and contact particulars are summarized in Table 2.3:
Table
2.3 Contact Details of Key Personnel
Party |
Role |
Post |
Name |
Contact No. |
Contact Fax |
AECOM |
Engineer¡¦s Representative for WDII |
Principal Resident Engineer |
Mr. Frankie Fan |
2587 1778 |
2587 1877 |
Engineer¡¦s Representative for CWB |
Principal Resident Engineer |
Mr. Peter Poon |
3912 3388 |
3912 3010 |
|
Chun Wo ¡V Leader Joint Venture |
Contractor under Contract no. HK/2009/01 |
Project Director |
|
2162 9909 |
2587 1878 |
Site Agent |
Mr. Paul Yu |
9456 9819 |
|||
Deputy Site Agent |
Mr Andy Yu |
96484896 |
|||
Construction Manager |
Mr Terry Wong |
9757 9846 |
|||
Construction Manager |
Mr. Wyman Wong |
9627 2467 |
|||
Construction Manager |
Mr. Jack Chu |
9775 3008 |
|||
Environmental Officer
(Compliance Manager) |
Mr. Andy Mak |
9103 2370 |
|||
Chun Wo ¡V CRGL Joint Venture |
Contractor under Contract no. HK/2009/02 |
Site Agent |
Mr. Chan Sing Cho |
3658 3002 |
2827 9996 |
Quality & Environmental Manager |
Mr. C.P. Ho |
9191 8856 |
|||
|
Contractor under Contract no. HY/2009/15 |
Project Director |
Chan Wai Hung |
2823 7813 |
2865 5229 |
Site Manager |
P J Fan |
3557 6368 |
2566 2192 |
||
|
|
Contractor¡¦s Representative |
Mr. David Lau |
3557 6358 |
|
|
|
Head of Construction Manager |
Roger Cheung |
3557 6371 |
|
|
|
Senior Construction Manager |
Gene Cheung |
3557 6395 |
|
|
|
Environmental Officer |
Mr. Daniel Sin |
3557 6347 |
|
Gammon -Leader JV |
Contractor under Contract no. HK/2010/06 |
Project Manager |
Mr. Paul Lui |
9095 7922 |
2529 2880 |
Site Agent |
Mr. Keith Tse |
2529 2068 |
|||
Environmental Officer |
Mr. Lee Wai Man |
9481
6024 |
|||
Chun Wo - CRGL - MBEC Joint Venture |
Contractor under Contract no. HY/2009/19 |
Project Manager |
Mr. Rayland Lee |
3758 8879 |
2570 8013 |
Site Agent |
Mr. Cheung Kit Cheung |
6909 1555 |
|||
Environmental Engineer |
Mr. Calvin Leung |
9286 9208 |
|||
Environmental Manager / Environmental Officer |
Mr. M.H. Isa |
9884 0810 |
|||
Construction Manager (Marine) |
William Luk |
9610 1101 |
|||
Construction Manager (Land) |
Patrick Cheung |
9643 3012 |
|||
Construction Manager (Land) |
Eric Fong |
6191 9337 |
|||
ENVIRON Hong Kong Limited |
Independent
Environmental Checker (IEC) |
Independent Environmental Checker (IEC) |
Mr. David Yeung |
3743 0788 |
3548 6988 |
Lam Geotechnics Limited |
Environmental Team (ET) |
Environmental Team Leader (ETL) |
Mr. Raymond Dai |
2882 3939 |
2882 3331 |
2.4.3.
For Contract no. HK/2009/01, the principal work
activities in this reporting month included:
Marine Works (at Wan Chai)
¡P
Rockfilling for HKCEC3E (East of HKCEC) between CH290 and CH385
¡P
Grouting works to pipe pile at
¡P
Removal of existing seawall and rock armour at
¡P
Dredging underneath
¡P
Fabrication of 3 nos. of precast concrete caisson seawall, 1 no. precast
concrete box culvert (namely Bay 10) and 2 nos. precast discharge outfall in
precasting yard at
Cross-Harbour Watermains
Installation (CHA & CHB) and Marine Works (at TST)
¡P
Rockfilling and rock protection to cross-harbour watermains
¡P
Thrust block construction for A18B18
¡P
Connection work between land pipeline and marine pipeline
¡P
Reinstatement works for the TST landfall
Fresh Watermains, Cooling
Watermains and Salt Watermains (On Land)
¡P
Mainlaying works at Zone B1-5A, B2-1, B3-1, A1-1, A1-2, A1-4, A1-2A
& A1-3A, A2-3D, A3-2A, A3-4B, A3-3C, C1-6 and run-out of Renaissance Hotel
¡P
Mainlaying works at TTA Zone A2-3D and A1-4
¡P
Pipe laying works at heading No. H1 and Zone A3-4B
¡P
Mainlaying works at Zone A3-3C
¡P
Mainlaying and chamber construction works at the traffic island near
junction of
¡P
Mainlaying works at
¡P
Final cleaning, CCTV inspection and pressure test for the 9 nos. cooling
watermains
E&M
¡P
Electrical works in cooling water pumping stations P5
¡P
Major cabling works from existing LV Switch-board Room to Cooling Water
Pumping Station P5
¡P
Power energization to L.V. switchboard for cooling water pumping
stations P5
¡P
Full commissioning for Cooling Water Pumping Stations P1
2.4.4.
For Contract no. HK/2009/02, the principal work
activities in this reporting month included:
¡P
Repairing of door hinges in the New Public Toilet..
¡P
Modification work of PTI at
¡P
Modification work of bus station at
¡P
Pre-inspection for P9 (SHK) Pumping Station.Reinstatement at
¡P
Cooling mains installation at west of Gate 1 inside ex-pet garden
¡P
Cooling main remedial works for the bending pipes
¡P
Installation of optic fiber and power cable
¡P
E&M works and ABWFs installation at WSD Salt Water Pumping Station
¡P
Concreting of boundary wall of EVA at WSD Pumping Station
¡P
Concreting of Inspection Manhole and Access Chamber of Salt Water Intake
Culvert at Bay 19B & 20
¡P
Concreting of the wall and top slab at salt water intake culvert Bay
¡P
Concreting of the blinding layer at salt water intake culvert Bay 9 -
Bay 11 at WCR1
¡P
Concreting of the wall and top slab at salt water intake culvert Bay 9
at WCR1 and steel fixing of base slab at Bay 10
¡P
Cutting the sheetpile wall at salt water intake culvert Bay 11 to
jacking pit
¡P
Concreting of wall and top slab of Bay
2.4.5.
For Contract no. HY/2009/15, the principal work
activities in this reporting month included:
¡P
TZ1 and TS2 reclamation works
¡P
Formation of temporary seawall at TS2
2.4.6.
For Contract no. HK/2010/06, the principal work
activities in this reporting month included:
¡P
Pile head breaking
¡P
Platform Disassembly
¡P
Bored Pile cutting
2.4.7.
For Contract no. HY/2009/19, the principal work
activity in this reporting month included:
¡P
Marine bored piling
¡P
Construction works for Box Culvert T
¡P
Construction of 1500f drainage pipe
2.4.8.
In coming reporting month, the principal work
activities of individual contracts are anticipated as follows:
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
Marine Works
¡P
Fabrication of precast concrete caisson seawalls, precast box culvert
(Bay 10) and precast discharge outfall in precasting yard at
¡P
Dredging works for Type 2 sediment underneath
¡P
Dredging works between CH290 and CH370 at east of HKCEC near Wan Chai
west ferry pier would be commenced after completion of removal of high spot of
Grade 75 rock fill along the submarine pipeline of cross-harbour watermains.
¡P
Excavation work and tie back system for construction of pipe pile wall
near expo drive East
¡P
Removal of seawall and rock armour at
¡P
Rockfilling at east of HKCEC near
¡P
Trust block construction at TST landfall
¡P
Rockfilling and rock armour protection works to cross-harbour watermains
¡P
Reinstatement works at TST seashore including removal of silt screen
¡P
Fresh water flushing, final cleaning and sterilizatioin for
cross-harbour watermains CHA, CHB, CHE & CHF
¡P
Installation of Impressed Current Cathodic Protection (ICCP) system to
CHA and CHB
Fresh Watermains, Cooling
Watermains and Salt Watermains (On Land)
¡P
Works would be continued at Zone B1-5A, B2-1, B3-1, A1-1, A1-2, A2-2,
A1-4(CHWM), A2-3D, A3-2A, A3-4B, A3-3C, run-out of Renaissance Hotel and C1-6
¡P
Mainlaying works at Zone C1-6
¡P
Reinstatement works at Zone B1-5A and B2-1
¡P
Mainlaying works at Zone B3-1
¡P
Mainlaying works at
¡P
Mainlaying works and grouting works at jacking pit in Zone A1-2A &
A1-3A of
¡P
Mainlaying works at traffic island near junction between
¡P
Pipe laying works for Heading no. H1 would be continued .The remaining
pipe works at Zone A3-2A
¡P
Mainlaying works at Zone A3-4B would be continued and the works at Zone
A3-4A & A3-5A would be subsequently commenced concurrently after the Zone
A3-4B had been completed reinstated and reopened to public.
¡P
Pressure test for the 1 no. cooling watermains (AF)
E&M Works
¡P
Electrical works in Cooling Water Pumping Stations P5
¡P
Power supply to cooling water pumping station P5 from L.V. switchboard
¡P
Initial commissioning for Cooling Water Pumping Stations P5
¡P
Power energization for Cooling Water Pumping Stations P5
¡P
Full commissioning for Cooling Water Pumping Stations P3, P4 & P5
Contract no. HK/2009/02 - Wan
Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
¡P
PTI modification works after completion of
New Public Toilet in
¡P
Complete all cooling mains and cabling works
for P7, P8 & P9 Pumping Stations permanent power-on and signal control.
¡P
800MS pipe installation inside
¡P
Modification work of EVA & Vehicle access
at WSD Pumping Station
¡P
Finishing works of WSD Salt Water Pumping
Station.
¡P
Construction of Bay 1b ¡V 2, Bay 6 ¡V 8 salt
water intake culverts at WCR1 area.
¡P
ELS of the salt water intake
¡P
Salt water intake culvert at transition bays
inside jacking pit and receiving pit.
¡P
Remaining drainage works and reinstatement works
along
¡P
HDPE piping inside outfall seaside cofferdam.
¡P
Construction for Box Culvert N1 at WCR1 area.
¡P
Concreting works for the Mezzanine Level at
the New Ferry Pier.
¡P
Seawall strengthening works at WCR2 area.
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V
Tunnel (
¡P
Formation of temporary seawall at TS2
¡P
TZ1 and TS2 reclamation works
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass over MTR Tsuen Wan Line
¡P
Pile head breaking
¡P
Platform Disassembly
¡P
Dredging
¡P
Bored Pile cutting
Contract no. HY/2009/19 ¡V Central- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
¡P
Construction
works for Box Culvert T
¡P
Marine Piling
¡P
Construction of
1500f drainage pipe
3.1.1.
A summary of the current status on licences and/or
permits on environmental protection pertinent to the Project is shown in Table
3.1.
Permits and/or Licences |
Reference No. |
Issued Date |
Status |
Environmental
Permit |
EP-356/2009 |
30 Jul
2009 |
Valid |
Environmental
Permit |
EP-364/2009/A |
4 Aug
2010 |
Superseded |
Environmental
Permit |
EP-364/2009/B |
17 Aug
2009 |
Valid |
Environmental
Permit |
EP-364/2009 |
17 Aug
2009 |
Superseded |
Environmental
Permit |
EP-376/2009 |
13 Nov 2010 |
Valid |
Further Environmental Permit |
FEP-01/356/2009 |
18 Feb
2010 |
Surrendered |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar
2010 |
Valid |
Further Environmental Permit |
FEP-03/356/2009 |
24 Mar
2010 |
Valid |
Further
Environmental Permit |
FEP-04/356/2009 |
22 Nov
2010 |
Valid |
Further
Environmental Permit |
FEP-05/356/2009 |
24 Mar
2011 |
Valid |
Further
Environmental Permit |
FEP-01/364/2009 |
24 Mar
2010 |
Valid |
Further
Environmental Permit |
FEP-02/364/2009 |
21 Apr 2010 |
Valid |
Further
Environmental Permit |
FEP-03/364/2009 |
12 Jul 2010 |
Valid |
Further
Environmental Permit |
FEP-04/364/2009/A |
14 Oct 2010 |
Surrendered |
Further
Environmental Permit |
FEP-05/364/2009/A |
15 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-06/364/2009/A |
22 Nov 2010 |
Valid |
Further
Environmental Permit |
FEP-07/364/2009/A |
25 Feb 2011 |
Valid |
Further
Environmental Permit |
FEP-08/364/2009/A |
15 Jun 2012 |
Valid |
3.1.2.
Due to the multi-contract nature of the Project,
the status of permits and/or licences under the individual contract(s) are
presented as below:
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
3.1.3.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission for contract no.
HK/2009/01 under FEP-02/356/2009 are shown in Table 3.4 and
Table 3.5.
Table
3.4 Cumulative Summary of Valid Licences
and Permits under Contract no. HK/2009/01
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-02/356/2009 |
24 Mar 2010 |
N/A |
Valid |
FEP-02/364/2009 |
21 Apr 2010 |
N/A |
Valid |
|
Notification of Works Under APCO |
313088 |
6 Jan 2010 |
N/A |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0460-12 |
10 May 2012 |
13 May 2012 to 6 Nov 2012 |
Expired |
|
GW-RS0514-12 |
14 May 2012 |
27 May 2012 to 26 Nov 2012 |
Expired |
|
GW-RS0855-12 |
16 Aug 2012 |
17 Aug 2012 to 9 Feb 2013 |
Cancelled |
|
GW-RS0862-12 |
20 Aug 2012 |
28 Aug 2012 to 27 Feb 2013 |
Cancelled |
|
GW-RS0949-12 |
12 Sep 2012 |
16 Sep 2012 to 15 Mar 2013 |
Cancelled |
|
GW-RS0545-12 |
24 May 2012 |
26 May 2012 to 25 Nov 2012 |
Expired |
|
GW-RS0546-12 |
25 May 2012 |
26 May 2012 to 25 Nov 2012 |
Expired |
|
GW-RS0760-12 |
18 Jul 2012 |
20 Jul 2012 to 19 Jan 2013 |
Valid |
|
GW-RS0806-12 |
3 Aug 2012 |
4 Aug 2012 to 03 Feb 2013 |
Cancelled |
GW-RS0823-12 |
3 Aug 2012 |
3 Aug 2012 to 02 Feb 2013 |
Cancelled |
|
GW-RS0852-12 |
16 Aug 2012 |
16 Aug 2012 to 01 Feb 2013 |
Cancelled |
|
GW-RS0994-12 |
25 Sep 2012 |
25 Sep 2012 to 19 Nov 2012 |
Expired |
|
GW-RS1011-12 |
26 Sep 2012 |
30 Sep 2012 to 29 Mar 2013 |
Cancelled |
|
GW-RS1017-12 |
27 Sep 2012 |
30 Sep 2012 to 24 Mar 2013 |
Valid |
|
GW-RE0793-12 |
21 Sep 2012 |
30 Sep 2012 to 29 Mar 2013 |
Valid |
|
|
GW-RS1040-12 |
8 Oct 2012 |
13 Oct 2012 to 12 Apr 2013 |
Valid |
GW-RS1177-12 |
15 Nov 2012 |
17 Nov 2012 to 10 May 2013 |
Valid |
|
GW-RS1184-12 |
15 Nov 2012 |
17 Nov 2012 to 8 May 2013 |
Valid |
|
GW-RS1185-12 |
19 Nov 2012 |
21 Nov 2012 to 8 May 2013 |
Valid |
|
GW-RS1179-12 |
20 Nov 2012 |
22 Nov 2012 to 21 May 2013 |
Valid |
|
GW-RS1187-12 |
20 Nov 2012 |
27 Nov 2012 to 26 May 2013 |
Valid |
|
|
GW-RS1199-12 |
20 Nov 2012 |
26 Nov 2012 to 25 May 2013 |
Valid |
Discharge Licence |
WT00006220-2010 |
18 Mar 2010 |
31 Mar 2015 |
Valid |
WT00009641-2011 |
24 Jul 2011 |
31 Jul 2016 |
Valid |
|
Billing account under Waste Disposal Ordinance |
7010069 |
21 Jan 2010 |
N/A |
Valid |
Registration as a Chemical Waste Producer |
WPN5213-134-C3585-01 |
21 Jan 2010 |
N/A |
Valid |
Dumping Permit (Type 1 ¡V |
EP/MD/13-004 |
23 May 2012 |
24 May 2012 to 23 Nov 2012 |
Expired |
Dumping Permit (Type 1 ¡V |
EP/MD/13-062 |
9 Oct 2012 |
10 Oct 2012 to 9 Nov
2012 |
Expired |
EP/MD/13-089 |
8 Nov 2012 |
12 Nov 2012 to 11 Dec 2012 |
Valid |
Table
3.5 Summary of submission status under
FEP-02/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 2.6 |
Management Organization of Main Construction Companies |
13 Apr 2010 |
Condition 2.7 |
Works Schedule and Location
Plan |
8 Apr 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan
(Rev. 5) |
24 Aug 2012 |
Silt Curtain Deployment Plan
(Rev. 4) |
12 July 2012 |
|
Condition 2.9 |
Silt Screen Deployment Plan |
19 Apr 2010 |
Silt Screen Deployment Plan
(Rev.4) |
15 Nov 2012 |
|
Conditions 2.8 and 2.9 |
Supplementary Document on Silt
Curtain and Silt Screen Deployment Plan |
19 Jul 2010 |
Report on Field Testing for
Silt Curtain |
26 Aug 2010 |
|
Report on Field Testing for
Silt Curtain (Rev. A) |
15 Nov 2010 |
|
Condition 2.12(d) |
Alternative Proposal on
Concurrent Dredging for Sewage Pipeline and |
15 Apr 2011 |
Condition 2.17 |
Noise Management Plan |
23 Apr 2010 |
Condition 2.18 |
Landscape Plan (Erection of
Decorative Screen Hoarding along Construction Site around |
15 May 2010 |
Landscape Plan (Night-time
Lighting) |
22 Oct 2010 |
|
Landscape Plan (Rev. B) |
15 Nov 2010 |
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
3.1.4.
Summary of the current
status on licences and/or permits on environmental protection pertinent and
submission for contract no. HK/2009/02 under FEP-03/356/2009 are shown in Table
3.6 and Table 3.7.
Table
3.6 Cumulative Summary of Valid Licences
and Permits under Contract no. HK/2009/02
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
FEP-03/356/2009 |
24 Mar 2010 |
N/A |
Valid |
|
|
FEP-01/364/2009 |
24 Mar 2010 |
N/A |
Valid |
Notification of Works Under APCO |
313962 |
2 Feb 2010 |
N/A |
Valid |
Construction Noise Permit (CNP) for non-piling equipment |
GW-RS0671-12 |
25 June 2012 |
17 Jul 2012 to 16 Jan 2013 |
Valid |
|
GW-RS0730-12 |
9 July 2012 |
10 Jul 2012 to 8 Jan 2013 |
Valid |
|
GW-RS0736-12 |
9 July 2012 |
9 Jul 2012 to 8 Jan
2013 |
Valid |
|
GW-RE0283-12 |
5 Apr 2012 |
1 May 2012 to 30 Nov 2012 |
Valid |
|
GW-RS0739-12 |
9 July 2012 |
1 Aug 2012 to 31 Jan 2013 |
Valid |
|
GW-RS1038-12 |
10 Oct 2012 |
10 Oct 2012 to 9 Apr 2013 |
Valid |
|
GW-RS1069-12 |
17 Oct 2012 |
19 Oct 2012 to 18 Apr 2013 |
Valid |
|
GW-RS0380-12 |
12 Apr 2012 |
1 May 2012 to 31 Oct 2012 |
Expired |
|
GW-RS0388-12 |
13 Apr 2012 |
1 May 2012 to 31 Oct 2012 |
Expired |
|
GW-RS0418-12 |
30 Apr 2012 |
23 May 2012 to 22 Nov 2012 |
Expired |
|
GW-RS0420-12 |
30 Apr 2012 |
18 May 2012 to 17 Nov 2012 |
Cancelled |
|
GW-RS0423-12 |
30 Apr 2012 |
19 May 2012 to 18 Nov 2012 |
Cancelled |
|
GW-RS0427-12 |
30 Apr 2012 |
23 May 2012 to 22 Nov 2012 |
Expired |
|
GW-RS0533-12 |
21 May 2012 |
21 May 2012 to 10 Nov 2012 |
Expired |
GW-RS0550-12 |
25 May 2012 |
7 June 2012 to 6 Dec 2012 |
Valid |
|
GW-RS0611-12 |
14 June 2012 |
15 Jun 2012 to 28 Nov 2012 |
Valid |
|
GW-RS0633-12 |
13 June 2012 |
16 Jun 2012 to 14 Dec 2012 |
Valid |
|
GW-RS0814-12 |
3 Aug 2012 |
6 Aug 2012 to 5 Dec 2012 |
Valid |
|
GW-RS0850-12 |
10 Aug 2012 |
14 Aug 2012 to 13 Feb 2013 |
Valid |
|
GW-RS0870-12 |
21 Aug 2012 |
16 Sept 2012 to 31 Dec 2012 |
Valid |
|
GW-RS0996-12 |
25 Sept 2012 |
26 Sept 2012 to 25 Mar 2013 |
Valid |
|
GW-RS1076-12 |
25 Oct 2012 |
1 Nov 2012 to 30 Apr 3013 |
Valid |
|
|
GW-RS1084-12 |
25 Oct 2012 |
1 Nov 2012 to 30 Apr 2013 |
Valid |
GW-RS1086-12 |
25 Oct 2012 |
28 Oct 2012 to 16 Apr 2013 |
Valid |
|
GW-RS1174-12 |
9 Nov 2012 |
11 Nov 2012 to 10 May 2013 |
Valid |
|
GW-RS1158-12 |
16 Nov 2012 |
18 Nov 2012 to 16 May 2013 |
Valid |
|
GW-RS1167-12 |
16 Nov 2012 |
23 Nov 2012 to 21 May 2013 |
Valid |
|
GW-RS1204-12 |
9 Nov 2012 |
29 Nov 2012 to 23 May 2013 |
Valid |
|
Discharge Licence |
WT00006249-2010 |
22 Mar 2010 |
31 Mar 2015 |
Valid |
WT00006436-2010 |
15 Apr 2010 |
30 Apr 2015 |
Valid |
|
WT00006673-2010 |
14 May 2010 |
31 Mar 2015 |
Cancelled |
|
WT00006757-2010 |
28 May 2010 |
31 May 2015 |
Valid |
|
WT00007129-2010 |
28 July 2010 |
31 Jul 2015 |
Valid |
|
WT00008982-2011 |
26 April 2011 |
30 April 2016 |
Valid |
|
WT00009691-2011 |
1 Aug 2011 |
31 July 2016 |
Valid |
|
Billing Account under Waste Disposal Ordinance (Land) |
7010255 |
10 Feb 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance (Marine) |
7011496 |
6 Oct 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer (Wan Chai) |
WPN5213-135-C3593-01 |
10 Mar 2010 |
N/A |
Valid |
Registration as Chemical Waste Producer (TKO 137) |
WPN5213-839-C3593-02 |
22 Sep 2010 |
N/A |
Valid |
Dumping Permit (Type 1 ¡V |
EP/MD/13015 |
25 May 2012 |
29 May 2012 to 28 Nov 2012 |
Expired |
EP/MD/13-095 |
19 Nov 2012 |
29 Nov 2012 to 28 May 2013 |
Valid |
|
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type
2 ¡V Confined Marine disposal) |
EP/MD/13-077 |
28 Sept 2012 |
6 Oct 2012 to 5 Nov 2012 |
Expired |
EP/MD/13-086 |
31 Oct 2012 |
6 Nov 2012 to 5 Dec 2012 |
Valid |
Table
3.7 Summary of submission status under
FEP-03/356/2009 Condition
EP Condition |
Submission |
Date of
Submission |
Condition 1.12 |
Commencement Date of
Construction of Marine Works |
8 April 2010 |
Condition 2.6 |
Management Organization of Main
Construction Companies |
10 April 2010 |
Condition 2.7 |
Works Schedule and Location
Plans |
8 April 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan
(Revision A) |
20 April 2010 |
Silt Curtain Deployment Plan
(Revision B) |
25 May 2010 |
|
Silt Curtain Deployment Plan
(Revision C) |
14 Jun 2010 |
|
Silt Curtain Deployment Plan
(Revision H) |
15 Feb 2011 |
|
Silt Curtain Deployment Plan
(Revision I) |
17 Nov 2011 |
|
Silt Curtain Deployment Plan
(Revision J) |
15 Feb 2012 |
|
Silt Curtain Deployment Plan
(Revision K) |
3 May 2012 |
|
Silt Curtain Deployment Plan
(Revision L) |
25 Oct 2012 |
|
Condition 2.9 |
Silt Screen Deployment Plan |
21 April 2010 |
Supplementary Information for
Existing WSD Salt Water Intakes at |
5 Oct 2010 |
|
Silt Screen Deployment Plan
(Revision B) |
15 Feb 2012 |
|
Silt Screen Deployment Plan
(Revision C) |
3 May 2012 |
|
Condition 2.17 |
Noise Management Plan |
6 May 2010 |
Condition 2.18 |
Landscape Plan (Decorative
Screen Hoarding) |
11 May 2010 |
Landscape Plan (Control of
Night Time Lighting) |
2 June 2010 |
|
Landscape Plan (Combined
Version) |
20 July 2011 |
|
Landscape Plan (Combined
Version) |
5 Aug 2011 |
|
----- |
Acknowledge of Submission |
22 Aug 2011 |
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V
Tunnel (
3.1.5.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission for contract no.
HY/2009/15 under EP-356/2009 are shown in Table 3.8 and
Table 3.9.
Table
3.8 Cumulative Summary of Valid Licences
and Permits under Contract no. HY/2009/15
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-04/356/2009 |
22 Nov 2010 |
N/A |
Valid |
FEP-06/364/2009/A |
22 Nov 2010 |
N/A |
Valid |
|
FEP-01/416/2011 |
11 Nov 2011 |
N/A |
Valid |
|
Notification of Works Under APCO |
321822 |
24 Sep 2010 |
N/A |
Valid |
Construction Noise Permit (CNP)
for Filling and Diaphragm Wall Works at TS4/ME4 |
GW-RS0924-12 |
31 Aug 2012 |
01 Sep 2012 to 28 Feb 2013 |
Cancelled |
GW-RS1191-12 |
26 Nov 2012 |
26 Nov 2012 to 11 May 2013 |
Valid |
|
Construction Noise Permit
(CNP) for bored pile construction at Eastern Breakwater of CBTS |
GW-RS1009-12 |
03 Oct 2012 |
03 Oct 2012 to 25 Mar 2013 |
Valid |
Construction Noise Permit (CNP)
for Removal Works at TS1 |
GW-RS0607-12 |
12 Jun 2012 |
13 Jun 2012 to 7 Dec 2012 |
Valid |
Construction Noise Permit (CNP)
for Dredging at TS2 |
GW-RS1023-12 |
05 Oct 2012 |
09 Oct 2012 to 25 Mar 2013 |
Valid |
Registration as a Chemical
Waste Producer |
WPN5213-147-C1169-35 |
15 Nov 2010 |
N/A |
Valid |
Billing Account under Waste Disposal Ordinance |
7011553 |
30 Sep 2010 |
27 Sep 2010 to 27 Jan 2016 |
Valid |
Billing Account under Waste Disposal Ordinance (Dumping by
Vessel) |
7011761 |
03 Oct 2012 |
17 Oct 2012 to 16 Jan 2013 |
Valid |
Dumping Permit (Type 1 ¡V |
EP/MD/13-018 |
6 Jun 2012 |
6 Jun 2012 to 5 Dec 2012 |
Valid |
Dumping Permit (Type 1 ¡V Open Sea Disposal (Dedicate
Sites) & Type 2 ¡V Confined Marine disposal) |
EP/MD/13-076 |
28 Sep 2012 |
8 Oct 2012 to 7 Nov 2012 |
Expired |
EP/MD/13-094 |
19 Nov 2012 |
24 Nov 2012 to 23 Dec 2012 |
Valid |
Table
3.9 Summary of submission status under
FEP-04/356/2009 Condition
FEP Condition |
Submission |
Date of Submission |
Condition 2.7 |
Works Schedule and Location Plans |
27 Oct 2010 |
|
Amendment for Works Schedule and Location Plans |
12 Nov 2010 |
Condition 2.8 |
Silt Curtain Deployment Plan |
30 Nov 2010 |
|
Amendment for Silt Curtain Deployment Plan |
24 Feb 2011 |
Amendment for Silt Curtain Deployment Plan |
11 May 2011 |
|
Amendment for Silt Curtain Deployment Plan |
11 Sep 2012 |
|
Amendment for Silt Curtain Deployment Plan |
30 Oct 2012 |
|
Condition 2.9 |
Silt Screen Deployment
Plan |
19 Oct 2010 |
Amendment for Silt Screen Deployment Plan |
18 Feb 2011 |
|
Amendment for Silt Screen Deployment Plan |
15 Jun 2011 |
|
Condition 2.18 |
Proposal for the Removal
of Odorous Sediment and Slime |
13 Jan 2011 |
Amendment for Proposal for the Removal of Odorous Sediment
and Slime |
8 Mar 2011 |
|
|
Amendment for Proposal for the Removal of Odorous Sediment
and Slime |
2 Aug 2011 |
Condition 2.21 |
Landscape Plan |
18 Feb 2011 |
Condition 2.23 |
Noise Management Plan |
20 Oct 2010 |
Amendment for Noise Management Plan |
27 Jan 2011 |
3.1.6.
Implementation status of the recommended mitigation
measures during this reporting period is presented in Appendix 3.1.
Contract no. HK/2010/06 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line
3.1.7.
Summary of the current status on licences and/or
permits on environmental protection pertinent and submission for contract no. HK/2010/06
under EP-356/2009 are shown in Table 3.10 and Table 3.11.
Table
3.10 Cumulative
Summary of Valid Licences and Permits under Contract no. HK/2010/06
Permits and/or Licences |
Reference No. |
Issued Date |
Valid Period/ Expiry Date |
Status |
Further Environmental Permit |
FEP-05/356/2009 |
24 Mar 2011 |
N/A |
Valid |
FEP-08/364//2009/A |
15 June 2012 |
N/A |
Valid |
|
Notification of Works Under APCO |
326344 |
18 Jan 2011 |
N/A |
Valid |
Construction Noise Permit (CNP) for piling equipment |
PP-RS0012-12 |
18 June 2012 |
6 Jul 2012 to 5 Jan 2013 |
Valid |
Construction Noise Permit (CNP)
for non-piling equipment |
GW-RS0989-12 |
21 Sept 2012 |
6 Oct 2012 to 5 Apr 2013 |
Valid |
GW-RS0658-12 |
21 June 2012 |
13 Jul 2012 to 12 Jan 2013 |
Valid |
|
Billing Account under Waste Disposal Ordinance |
7012338 |
16 Feb 2011 |
N/A |
Valid |
Registration as Chemical Waste Producer |
WPN5213-134-G2533-01 |
11 Feb 2011 |
N/A |
Valid |
Water Discharge Licence |
WT00010905-2011 |
4 November 2011 |
31 July 2016 |
Valid` |
Table
3.11 Summary of
submission status under EP-356/2009 and FEP-05/356/2009 Condition
EP Condition |
Submission |
Date
of Submission |
Condition 2.6 |
Management Organization of Main Construction Companies |
24 October 2011 |
Condition
2.7 |
Works
Schedule and Location Plans |
11 March
2011 |
Condition
2.8 |
Revised
Silt Curtain Deployment Plan |
31 Aug 2011 |
Revised
Silt Curtain Deployment Plan |
22 Oct
2012 |
|
Revised Silt Curtain Deployment Plan |
26 Nov 2012 |
|
Condition
2.9 |
Silt
Screen Deployment Plan |
11 April
2011 |
Condition
2.23 |
Noise
Management Plan |
11 March 2011 |
Contract no. HY/2009/19 ¡V Central- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
3.1.8.
Summary of the current status on licences and/or
permits on environmental protection pertinent for contract no. HY/2009/19 is
shown in Table 3.12.
Table 3.12 Cumulative
Summary of Valid Licences and Permits under Contract no. HY/2009/19
Permit / Licence / Notification / Approval |
Reference No. |
Issued Date |
Valid Period / Expiry date |
Status |
Further Environmental Permit |
FEP-07/364/2009/A |
25 Feb 2011 |
Granted |
Valid |
Notification of Works Under APCO |
326160 |
24 Jan 2011 |
Notified |
Valid |
Construction Noise Permit (CNP) (For D-wall construction)
(Portion I, VII, VIII & IX) |
GW-RS0871-12 |
27-Aug-12 |
26-Feb-13 |
Valid |
Construction Noise Permit (CNP)
(For Bored pile construction at Portion III) |
GW-RS0507-12 |
22-May-12 |
23-Nov-12 |
Cancelled |
Construction Noise Permit (CNP)
(For Bored pile construction at Portion III, V) |
GW-RS0885-12 |
27-Aug-12 |
26-Feb-13 |
Valid |
Construction Noise Permit (CNP) (For |
GW-RS0589-12 |
18-Jun-12 |
17-Dec-12 |
Cancelled |
GW-RS1230-12 |
28-Nov-12 |
25-May-13 |
Valid |
|
Construction Noise Permit (CNP)
(For IEC) |
GW-RS0953-12 |
17-Sep-12 |
20-Mar-13 |
Cancelled |
GW-RS1210-12 |
29-Nov-12 |
28-May-13 |
Valid |
|
Construction Noise Permit (CNP)
(For IEC Parapet Removal ¡V Loading/Unloading) |
GW-RS1065-12 |
16-Oct-12 |
20-Apr-13 |
Valid |
Discharge Licence (Land) |
WT00010093-2011 |
17 Aug 2012 |
30-Sept-16 |
Valid |
Discharge Licence (Sea) |
WT00010865-2011 |
03 Nov 2011 |
30-Nov-16 |
Valid |
Registration as a Waste Producer |
7012306 |
21 Jan 2011 |
Registered |
- |
C&D
Waste Disposal |
7012306 |
10 Feb 2011 |
Registered |
- |
Vessel
Disposal |
7013285 |
21 July 2011 |
Registered |
- |
Registration
as Chemical Waste Producer |
5213-151-C3654-01 |
24 Mar 2011 |
Registered |
- |
Dumping
Permit (Type 1 ¡V |
EP/MD/12-150 |
14-May-12 |
14-Nov-12 |
Expired |
Noise Monitoring Stations
4.1.1.
The noise monitoring stations for the Project are
listed and shown in Table 4.1 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table 4.1 Noise
Monitoring Station
Station |
Description |
M1a |
Harbour
Road Sports Centre |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
M4b |
Victoria
Centre |
M5b |
|
M6 |
HK |
Real-time Noise Monitoring Stations
4.1.2.
The real-time noise monitoring stations for the
Project are listed and shown in Table 4.2 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
4.1.3.
The real-time noise monitoring at RTN2-Oil Street
Community Liaison Centre has been relocated to City Garden Electric Centre
(RTN2a- Electric Centre) on 5 Oct 2012, which is a representative of noise
sensitive
4.1.4.
As the land-based piling and filling works- DP3 at
Tin Hau had been completed on 3 September 2012 and confirmed by RSS, the
real-time noise monitoring results at FEHD Hong Kong Transport Section
Whitfield Depot was excluded under EP-356/2009 since 28 November 2012.
Table 4.2 Real
Time Noise Monitoring Station
District |
Station |
Description |
Tin
Hau |
RTN1 |
FEHD Hong Kong Transport Section
Whitfield Depot |
North Point |
RTN2 |
Oil Street Community Liaison Centre |
North Point |
RTN2a |
Electric Centre |
Noise Monitoring Parameters, Frequency and Duration
4.1.5.
The construction noise
level shall be measured in terms of the A-weighted equivalent continuous sound
pressure level (Leq). Leq (30 minutes) shall be used as
the monitoring parameter for the time period between 0700 and 1900 hours on
normal weekdays. For all other time periods, Leq (5 minutes) shall
be employed for comparison with the Noise Control Ordinance (NCO) criteria.
Supplementary information for data auditing, statistical results such as L10
and L90 shall also be obtained for reference.
4.1.6.
Noise monitoring shall be carried out at all the
designated monitoring stations. The monitoring frequency shall depend on the
scale of the construction activities. The following is an initial guide on the
regular monitoring frequency for each station on a weekly basis when noise
generating activities are underway:
¡P
one set of
measurements between 0700 and 1900 hours on normal weekdays.
4.1.7.
If construction works are extended to include works
during the hours of 1900 ¡V 0700 as well as public holidays and Sundays,
additional weekly impact monitoring shall be carried out during respective
restricted hours periods. Applicable permits under NCO shall be obtained by the
Contractor.
Monitoring Equipment
4.1.8.
As referred to in the Technical Memorandum ™ issued
under the NCO, sound level meters in compliance with the International
Electrotechnical Commission Publications 651: 1979 (Type 1) and 804: 1985 (Type
1) specifications shall be used for carrying out the noise monitoring.
Immediately prior to and following each noise measurement the accuracy of the
sound level meter shall be checked using an acoustic calibrator generating a
known sound pressure level at a known frequency. Measurements may be accepted
as valid only if the calibration level from before and after the noise
measurement agree to within 1.0 dB.
4.1.9.
Noise measurements shall not be made in fog, rain,
wind with a steady speed exceeding 5 m/s or wind with gusts exceeding 10 m/s.
The wind speed shall be checked with a portable wind speed meter capable of
measuring the wind speed in m/s.
Air Quality Monitoring Stations
4.2.1.
The air monitoring stations for the Project are
listed and shown in Table 4.3 and Figure 4.1. Appendix 4.1 shows the established
Action/Limit Levels for the monitoring works.
Table
4.3 Air Monitoring Station
Station ID |
Monitoring Location |
Description |
CMA1b |
Oil Street Community Liaison Centre |
North
Point |
CMA2a |
|
|
CMA3a |
CWB PRE
Site Office * |
|
CMA4a |
Society for the Prevention of
Cruelty to Animals |
Wan Chai |
CMA5a |
Children Playgrounds opposite to |
Wan Chai |
CMA6a |
WDII PRE
Site Office * |
Wan Chai |
* Remarks:
As per the ENPC meeting in January 2011, the monitoring stations CMA3a - Future
CWB site office at Wanchai Waterfront Promenade and CMA6a - Future AECOM site
office at Work Area were renamed as remark.
Air Monitoring Parameters, Frequency and Duration
4.2.2.
One-hour and 24-hour TSP levels should be measured
to indicate the impacts of construction dust on air quality. The 24-hour TSP
levels shall be measured by following the standard high volume sampling method
as set out in the Title 40 of the Code of Federal Regulations, Chapter 1 (Part
50), Appendix B.
4.2.3.
All relevant data including temperature, pressure,
weather conditions, elapsed-time meter reading for the start and stop of the
sampler, identification and weight of the filter paper, and any other local
atmospheric factors affecting or affected by site conditions, etc., shall be
recorded down in detail.
4.2.4.
For regular impact monitoring, the sampling
frequency of at least once in every six-days, shall be strictly observed at all
the monitoring stations for 24-hour TSP monitoring. For 1-hour TSP monitoring,
the sampling frequency of at least three times in every six-days should be
undertaken when the highest dust impact occurs.
Sampling Procedure and Monitoring Equipment
4.2.5.
High volume samplers (HVSs) in compliance with the
following specifications shall be used for carrying out the 1-hour and 24-hour
TSP monitoring:
¡P
0.6 - 1.7 m3 per
minute adjustable flow range;
¡P
equipped with a
timing / control device with +/- 5 minutes accuracy for 24 hours operation;
¡P
installed with
elapsed-time meter with +/- 2 minutes accuracy for 24 hours operation;
¡P
capable of
providing a minimum exposed area of 406 cm2;
¡P
flow control
accuracy: +/- 2.5% deviation over 24-hour sampling period;
¡P
equipped with a
shelter to protect the filter and sampler;
¡P
incorporated
with an electronic mass flow rate controller or other equivalent devices;
¡P
equipped with a
flow recorder for continuous monitoring;
¡P
provided with a
peaked roof inlet;
¡P
incorporated
with a manometer;
¡P
able to hold and
seal the filter paper to the sampler housing at horizontal position;
¡P
easily
changeable filter; and
¡P
capable of
operating continuously for a 24-hour period.
4.2.6.
Initial calibration of dust monitoring equipment
shall be conducted upon installation and thereafter at bi-monthly intervals.
The transfer standard shall be traceable to the internationally recognized
primary standard and be calibrated annually. The concern parties such as IEC
shall properly document the calibration data for future reference. All the data
should be converted into standard temperature and pressure condition.
Laboratory Measurement / Analysis
4.2.7.
A clean laboratory with constant temperature and
humidity control, and equipped with necessary measuring and conditioning
instruments to handle the dust samples collected, shall be available for sample
analysis, and equipment calibration and maintenance. The laboratory should be
HOKLAS accredited.
4.2.8.
An alternative non-HOKLAS
accredited laboratory was set-up for carrying out
the laboratory analysis, the laboratory equipment was approved by the ER
on 8 February 2011 and the measurement procedures were witnessed by the IEC. Any measurement performed by the laboratory was be demonstrated to the satisfaction of the ER and IEC. IEC shall
regularly audit to the measurement performed by the laboratory to ensure the
accuracy of measurement results.
4.2.9.
Filter paper of size 8" x 10" shall be
labelled before sampling. It shall be a clean filter paper with no pinholes,
and shall be conditioned in a humidity-controlled chamber for over 24-hours and
be pre-weighed before use for the sampling.
4.2.10. After
sampling, the filter paper loaded with dust shall be kept in a clean and
tightly sealed plastic bag. The filter paper shall then be returned to the
laboratory for reconditioning in the humidity controlled chamber followed by
accurate weighing by an electronic balance with readout down to 0.1 mg. The
balance shall be regularly calibrated against a traceable standard.
4.2.11. All the
collected samples shall be kept in a good condition for 6 months before
disposal.
impact monitoring for odour patrol
4.2.12. Odour
patrols along the shorelines of Causeway Bay Typhoon Shelter and ex-Wan Chai
Public Cargo Working Area when there is temporary reclamation in Causeway Bay
Typhoon Shelter and/or in the ex-Wan Chai Public Cargo Working Area, or when
there is dredging of the odorous sediment and slime at the south-western corner
of the Causeway Bay Typhoon Shelter. Odour patrols will be carried out at
bi-weekly intervals during July, August and September by a qualified person of
the ET who shall:
¡P
be at least 16
years of age;
¡P
be free from any
respiratory illnesses; and
¡P
not be allowed
to smoke, eat, drink (except water) or use chewing gum or sweets 30 min
¡P
before and
during odour patrol
4.2.13. Odour
patrol shall be conducted by independent trained personnel / competent persons
patrolling and sniffing around the shore as shown in Figure 4.1 to detect any
odour at the concerned hours (afternoon is preferred for higher daily
temperature).
4.2.14. The
qualified person will use the nose (olfactory sensor) to sniff odours at
different locations. The main odour emission sources and the areas to be affected
by the odour nuisance will be identified.
4.2.15. The
perceived odour intensity is to be divided into 5 levels which are ranked in
the descending order as follows:
¡P
0 - Not
detected. No odour perceived or an odour so weak that it cannot be easily characterized
or described;
¡P
1 - Slight
Identifiable odour, and slight chance to have odour nuisance;
¡P
2 - Moderate
Identifiable odour, and moderate chance to have odour nuisance;
¡P
3 - Strong
Identifiable, likely to have odour nuisance;
¡P
4 - Extreme
Severe odour, and unacceptable odour level.
4.2.16.
The findings including odour intensity, odour
nature and possible odour sources, and also the local wind speed and direction
at each location will be recorded. In addition, some relevant meteorological
and tidal data such as daily average temperature, and daily average humidity,
on that surveyed day will be obtained from the Hong Kong Observatory Station
for reference. The Action and Limit levels for odour patrol are shown in Appendix 6.1.
4.2.17. The
qualified odour patrol member has individual n-butanol thresholds complied with
the requirement of European Standard Method of Air Quality ¡V Determination of
Odour Concentration by Dynamic Olfactometry (EN13725) in the range of 20 to 80
ppb.
4.3.1.
The EIA Report has identified that the key water
quality impact would be associated with the dredging works during the
construction phase. Marine water quality monitoring for dissolved oxygen (DO),
suspended solid (SS) and turbidity is therefore recommended to be carried out
at selected WSD flushing water intakes. The impact monitoring should be carried
out during the proposed dredging works to ensure the compliance with the water
quality standards.
4.3.2.
The updated EM&A Manual for EP-356/2009
(Version in March 2011) is approval by EPD on 29 April 2011. As such, the
Action Level and Limit Level for the wet season (April ¡V September) will be
effected and applied to the water quality monitoring data from 30 April 2011.
Water Quality Monitoring Stations
4.3.3.
It is proposed to monitor the water quality at 9
WSD salt water intakes and 14 cooling water intakes along the seafront of the
Table 4.4 Marine
Water Quality Stations for Water Quality Monitoring
Station Ref. |
Location |
Easting |
Northing |
WSD Salt
Water Intake |
|||
WSD7 |
|
834150.0 |
818300.3 |
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
WSD10 |
Cha Kwo Ling |
841900.9 |
817700.1 |
WSD15 |
Sai Wan Ho |
841110.4 |
816450.1 |
WSD17 |
|
839790.3 |
817032.2 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
|
830750.6 |
816030.3 |
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
RW1 |
Wan Chai (Reprovision) |
836188.8 |
815911.1 |
Cooling
Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C2 |
Telecom House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase I |
835836.2 |
815910.0 |
C4e |
Great Eagle Centre |
835932.8 |
815888.2 |
C4w |
Wan |
835629.8 |
815889.2 |
C5e |
Sun Hung Kai Centre (Eastern) |
836250.1 |
815932.2 |
C5w |
Sun Hung Kai Centre (Western) |
836248.1 |
815933.2 |
C6 |
Excelsior
Hotel |
837009.6 |
815999.3 |
C7 |
|
837193.7 |
816150.0 |
C8 |
|
837970.6 |
816957.3 |
C9 |
Provident Garden |
838355.0 |
817116.6 |
RC1 |
Proposed
HKAPA Extension |
835487.7 |
815987.7 |
RC5 |
Sun Hung
Kai Centre (Reprovision) |
836291.4 |
816029.7 |
RC7 |
|
837245.2 |
816156.6 |
Water Quality Parameters
4.3.4.
Monitoring of dissolved oxygen (DO), turbidity and
suspended solids (SS) shall be carried out at WSD flushing water intakes and
cooling water intakes. DO and Turbidity are measured in-situ while SS is
determined in laboratory.
4.3.5.
In association with the water quality parameters,
other relevant data shall also be measured, such as monitoring
location/position, time, sampling depth, water temperature, pH, salinity,
dissolved oxygen (DO) saturation, weather conditions, sea conditions, tidal
stage, and any special phenomena and work underway at the construction site
etc.
Sampling Procedures and Monitoring Equipment
4.3.6.
The interval between two sets of monitoring should
not be less than 36 hours except where there are exceedances of Action and/or
Limit Levels, in which case the monitoring frequency will be increased. Table
4.5 shows the proposed monitoring frequency and water quality
parameters. Duplicate in-situ measurements and water sampling should be carried
out in each sampling event. For selection of tides for in-situ measurement and
water sampling, tidal range of individual flood and ebb tides should be not
less than 0.5m.
Table 4.5 Marine
Water Quality Monitoring Frequency and Parameters
Activities |
Monitoring Frequency1 |
Parameters2 |
During the 4-week baseline
monitoring period |
Three days per week, at mid-flood
and mid-ebb tides |
Turbidity, Suspended Solids (SS),
Dissolved Oxygen (DO), pH, Temperature, Salinity |
During marine
construction works |
Three days per week, at mid-flood
and mid-ebb tides |
Turbidity, Suspended Solids (SS),
Dissolved Oxygen (DO), pH, Temperature, Salinity |
After
completion of marine construction works |
Three days per week, at mid-flood
and mid-ebb tides |
Turbidity, Suspended Solids (SS),
Dissolved Oxygen (DO), pH, Temperature, Salinity |
Notes:
1.
For selection of tides for in-situ measurement and water
sampling, tidal range of individual flood and ebb tides should be not less than
0.5m.
2.
Turbidity should be measured in situ whereas SS should be
determined by laboratory.
Dissolved Oxygen and Temperature Measuring
Equipment
4.3.7.
The instrument should be a portable, weatherproof
dissolved oxygen measuring instrument complete with cable, sensor,
comprehensive operation manuals, and use a DC power source. It should be
capable of measuring:
¡P
a dissolved
oxygen level in the range of 0-20 mg/l and 0-200% saturation
¡P
a temperature of
0-45 degree Celsius
4.3.8.
It should have a membrane electrode with automatic
temperature compensation complete with a cable. Sufficient stocks of spare
electrodes and cables should be available for replacement where necessary.
(e.g. YSI model 59 meter, YSI 5739 probe, YSI 5795A submersible stirrer with
reel and cable or an approved similar instrument).
4.3.9.
Should salinity compensation not be build-in in the
DO equipment, in-situ salinity shall be measured to calibrate the DO equipment
prior to each DO measurement.
Turbidity Measurement Instrument
4.3.10. The
instrument should be a portable, weatherproof turbidity-measuring instrument
complete with comprehensive operation manual. The equipment should use a DC
power source. It should have a photoelectric sensor capable of measuring
turbidity between 0‑1000 NTU and be complete with a cable (e.g. Hach model
2100P or an approved similar instrument).
Sampler
4.3.11. A water
sampler comprises a transparent PVC cylinder, with a capacity of not less than
2 litres, and can be effectively sealed with latex cups at both ends. The
sampler should have a positive latching system to keep it open and prevent
premature closure until released by a messenger when the sampler is at the
selected water depth (e.g. Kahlsico Water Sampler or an approved similar
instrument).
Sample Container and Storage
4.3.12. Water
samples for suspended solids measurement should be collected in high-density
polythene bottles, packed in ice (cooled to 4¢XC without being frozen), and
delivered to ALS Technichem (HK) Pty Ltd. as soon as possible after collection
for analysis.
Water Depth Detector
4.3.13. A
portable, battery-operated echo sounder shall be used for the determination of
water depth at each designated monitoring station. This unit can either be
handheld or affixed to the bottom of the workboat, if the same vessel is to be
used throughout the monitoring programme.
Salinity
4.3.14. A portable
salinometer capable of measuring salinity in the range of 0-40 ppt shall be
provided for measuring salinity of the water at each of monitoring location.
Monitoring Position Equipment
4.3.15. A
hand-held or boat-fixed type digital Global Positioning System (GPS) with
waypoint bearing indication or other equivalent instrument of similar accuracy
shall be provided and used during monitoring to ensure the monitoring vessel is
at the correct location before taking measurements.
Calibration of In-situ Instruments
4.3.16. All in-situ
monitoring instrument shall be checked, calibrated and certified by a
laboratory accredited under HOKLAS or equivalent before use, and subsequently
re-calibrated at 3 monthly intervals throughout all stages of the water quality
monitoring. Responses of sensors and electrodes should be checked with
certified standard solutions before each use. Wet bulb calibration for a DO
meter shall be carried out before measurement at each monitoring location.
4.3.17. For the on
site calibration of field equipment by the ET, the BS 127:1993, "Guide to
Field and on-site test methods for the analysis of waters" should be
observed.
4.3.18. Sufficient
stocks of spare parts should be maintained for replacements when necessary.
Backup monitoring equipment shall also be made available so that monitoring can
proceed uninterrupted even when some equipment is under maintenance,
calibration, etc.
4.3.19. Current
calibration certificates of equipments are presented in Appendix
4.2.
Laboratory Measurement / Analysis
4.3.20. Analysis
of suspended solids has been carried out in a HOKLAS accredited laboratory, ALS
Technichem (HK) Pty Ltd. Water samples of about 1L shall be collected at the
monitoring stations for carrying out the laboratory SS determination. The SS
determination work shall start within 24 hours after collection of the water
samples. The SS determination shall follow APHA 19ed or equivalent methods
subject to the approval of IEC and EPD.
Enhanced Water Quality
Monitoring in the ex-Wan Chai Public Cargo
Working Area and the
4.3.21. The
enhanced water quality monitoring and audit programme is to avoid aggravation
of odour nuisance from seawater arising from temporary reclamation in the
ex-Wan Chai Public Cargo Working Area and the Causeway Bay Typhoon Shelter.
4.3.22. Dissolved
oxygen monitoring at the intakes C6 and C7 in Causeway Bay Typhoon Shelter when
there is temporary reclamation in Causeway Bay Typhoon Shelter and at the
south-western and south-eastern corners of the ex-Wan Chai Public Cargo Working
Area. The proposed water quality monitoring stations of the Project are shown
in Table 4.6 and Figure 4.1.
Table
4.6 Marine Water
Quality Stations for Enhanced Water Quality Monitoring
Station |
Location |
C6 |
Excelsior
Hotel |
C7 |
|
Ex-WPCWA-SW |
South-western
of the ex-Wan Chai Public Cargo Working Area |
Ex-WPCWA-SE |
South-eastern
of the ex-Wan Chai Public Cargo Working Area |
4.3.23. The
monitoring of dissolved oxygen are to be carried out 3 days per week, at
mid-flood and mid-ebb tides for 3 water depths (1m below water surface,
mid-depth and 1m above sea bed, except where the water depth less than 6m, the
mid-depth may be omitted. If the water depth be equal to or less than 3m, only
the mid-depth will be monitored).
Daily SS Monitoring and 24
hours Turbidity Monitoring System
4.3.24.
During dredging of the sediment at the
south-western corner of the Causeway Bay Typhoon Shelter, daily monitoring of
suspended solids and 24 hour monitoring of turbidity at the cooling water
intakes (C6 and C7) shall be conducted.
4.3.25.
The 24 hours monitoring of turbidty at the cooling water
intakes (C6 and C7) shall be established by setting up a continuous water quality
monitoring station in front of the intakes during the dredging activities. The
monitoring system include the turbidity sensor and data logger which is capable
of data capturing at every 5 minutes. The data sahll be downloaded daily and
compared with the Action and Limit level determined during the baseline water
qualtiy monitoring at the cooling water intake locations.
Additional Dissovled
oxygen Monitoring FOR CULVERT L WATER DISCHARGE FLOW
4.3.26.
In
response to the Condition 2.18 of the Environmental Permit no. EP-356/2009
requiring that a silt curtain / impermeable barrier system be installed to
channel water discharge flow from Culvert L to locations outside the embayment
area, a proposed replacement of the requirement with additional dissolved
oxygen monitoring has been conducted at three monitoring stations, namely A, B
and C between the eastern seawall of Central Reclamation Phase III and the
HKCEC Extension since November 2011 under EP-356/2009 so that DO level between
the eastern seawall of Central Reclamation Phase II and the HKCEC extension
could be continuously monitored.
4.3.27. The
proposed DO monitoring stations of the Project are shown in Table 4.7 and
Figure 4.1.
Table
4.7 Marine Water
Quality Stations for Additional DO Monitoring
Station |
Easting |
Northing |
A |
835468 |
815857 |
B |
835572 |
815961 |
C |
835659 |
816271 |
4.3.28.
The monitoring of dissolved oxygen are to be
carried out once per week, at mid-flood and mid-ebb tides for 3 water depths
(1m below water surface, mid-depth and 1m above sea bed, except where the water
depth less than 6m, the mid-depth may be omitted. If the water depth be equal
to or less than 3m, only the mid-depth will be monitored).
5.0.1.
The environmental monitoring will be implemented
based on the division of works areas of each designed project managed under
different contracts with separate FEP applied by individual contractors.
Overall layout showing work areas of various contracts, latest status of work
commencement and monitoring stations is shown in Figure
2.1 and Figure 4.1. The monitoring
results are presented in according to the Individual Contract(s).
5.0.2.
In the reporting month, the concurrent contracts
are as follows:
Contract no. HK/2009/01 ¡V Wan Chai Development Phase II ¡V Central-Wan
Chai Bypass at
Contract no. HK/2009/02 Wan Chai Development Phase II ¡V Central-Wan Chai
Bypass at Wan Chai East
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
Contract no. HK/2010/06 Wan Chai Development Phase II ¡V Central-Wan Chai
Bypass over MTR Tsuen Wan Line
Contract no. HY/2009/19- Cental- Wan Chai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link
5.0.3.
The environment monitoring schedules for reporting
month and coming month are presented in Appendix
5.1.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC, Contract no. HK/2009/02 - Wan Chai
Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East and Contract
no. HK/2010/06 Wan Chai Development Phase II ¡V Central-Wan Chai Bypass over MTR
Tsuen Wan Line
5.1.1.
The proposed division of noise monitoring stations
are summarized in Table 5.2 below.
Table 5.2 Noise
Monitoring Station for Contract nos. HK/2009/01, HK/2009/02 and HK/2010/06
Station |
Description |
M1a |
Harbour Road Sports Centre |
5.1.2.
Daytime and evening period noise monitoring was
conducted at the Harbour Road Sport Centre in the reporting month.
5.1.3.
No exceedance was recorded in this reporting
period. Details of noise monitoring results and graphical presentation can be
referred in Appendix
5.2
Contract
no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
5.1.4.
The noise monitoring for HY/2009/15 was commenced
on 10 November 2010. The proposed division of noise monitoring stations are
summarized in Table 5.3 below.
Table 5.3 Noise Monitoring Station for Contract no. HY/2009/15
Station |
Description |
M2b |
Noon Gun Area |
M3a |
Tung Lo Wan Fire Station |
5.1.5.
Noise monitoring results measured in the period of
daytime and restricted hour are reviewed and summarized. No exceedance was
recorded in this reporting period. Details of noise monitoring results and
graphical presentation can be referred in
Appendix 5.2
Contract no. HY/2009/19- Wan Chai Bypass Tunnal
(North Point Section) and Island Eastern Corridor Link
5.1.6.
The proposed division of noise monitoring stations
are summarized in Table 5.4 below.
Table 5.4 Noise Monitoring Station for Contract no. HY/2009/19
Station |
Description |
M3a |
Tung Lo
Wan Fire Station |
M4b |
Victoria
Centre |
M5b |
|
M6 |
HK |
5.1.7.
No action level exceedance and two limit level
exceedances were recorded at M6 on 1 and 6 November 2012. Details of noise
monitoring results and graphical presentation can be referred in Appendix
5.2
Contract no. HY/2009/19 ¡V
Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern
Corridor Link
5.2.1
As the land-based piling and filling works- DP3 at Tin Hau had been
completed on 3 September 2012 and confirmed by RSS, the real-time noise
monitoring results at FEHD Hong Kong Transport Section Whitfield Depot was
excluded under EP-356/2009 since 28 November 2012.
5.2.2
The real-time noise monitoring at RTN2-Oil Street Community Liaison
Centre has been relocated to City Garden Electric Centre (RTN2a- Electric
Centre) on 5 Oct 2012, which is a representative of noise sensitive
5.2.3
The major work activities for Contract no. HY/2009/11 was confirmed substantial
complete by RSS on 4 January 2012. The construction site was handed over to
contractor HY/2009/19 on 31 December 2011 and the FEP-01/356/2009 was
surrendered on 22 Oct 2012.
5.2.4
No exceedance was recorded in this reporting month.
5.2.5
Real-time noise monitoring at FEHD Hong Kong
Transport Section Whitfield Depot commenced external wall renovation since 1
June 2012
Table 5.5 Real
Time Noise Monitoring Station for Contract no. HY/2009/19
District |
Station |
Description |
Tin Hau |
RTN1 |
FEHD Hong Kong
Transport Section Whitfield
Depot |
North Point |
RTN2 |
Oil Street
Community Liaison Centre |
North Point |
RTN2a |
Electric Centre |
l
Real
time noise monitoring results and graphical presentation during night time
period are for information only.
l
RTN2 had been relocated to RTN2a since 5 Oct 2012
l
RTN1 monitoring had been finished on 28 Nov 2012
5.2.6
Details of real time noise monitoring results and
graphical presentation can be referred to Appendix
5.5.
5.3.1.
Due to extension of site boundary by contractor of
HY/2009/19, location of air monitoring station CMA1b ¡V Oil Street Community
Liaison Centre has been finely adjusted on 21 April 2012.
5.3.2.
Due to lack of electricity supply, the 24-hr TSP
monitoring at the following stations were rescheduled:
CMA2a: from 8 and 14 November 2012 to 9 and 15
November 2012
CMA5a: from 8 November 2012 to 9 November 2012
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
5.3.3.
Air monitoring was commenced on 1 April 2011 in
response to the commencement of the land-filling work for Contract no.
HK/2009/01. The proposed divisions of air monitoring stations are summarized in
Table 5.7 below. No exceedance was recorded in the reporting
month.
Table 5.7 Air
Monitoring Stations for Contract no. HK/2009/01
Station |
Description |
CMA5a |
Children Playgrounds opposite to |
CMA6a |
WDII PRE Site Office |
Contract no. HK/2009/02 - Wan Chai Development
Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
5.3.4.
Air monitoring was commenced in mid-January 2011
for the land-filling work for Contract no. HK/2009/02. The proposed division of
air monitoring stations are summarized in Table 5.8 below. No
exceedance was recorded in the reporting month.
Table 5.8 Air
Monitoring Station for Contract no. HK/2009/02
Station |
Description |
CMA4a |
Society for the Prevention of Cruelty to Animals |
Contract no.
HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
5.3.5.
Air monitoring was commenced on 15 March 2011 for
the land filling work for Contract no. HY/2009/15. The proposed division of air
monitoring stations are summarized in Table 5.9 below. No
exceedance was recorded in the reporting month.
Table
5.9 Air
Monitoring Station for Contract no. HY/2009/15
Station |
Description |
CMA3a |
CWB PRE Site Office |
Contract no.
HY/2009/19- Wan Chai Bypass Tunnal (North Point Section) and Island Eastern
Corridor Link
5.3.6.
The proposed division of air monitoring stations
are summarized in Table 5.10 below. No exceedance was recorded in the reporting
month.
Table 5.10 Air Monitoring Stations for Contract no.
HY/2009/19
Station |
Description |
CMA1b |
Oil St Community Liaison Centre |
CMA2a |
|
5.4.1.
Based
on the safety concern when the lighting system for the access to C3 was off on
3 and 6 Nov 2012 during ebb tide and flood tide, the water quality monitoring
were cancelled on 3 and 6 November during ebb tide and flood tide.
5.4.2.
Based
on the safety concern when the lighting system for the access to C3 was off, the
water quality monitoring were cancelled in the following dates and tides:
2 Nov 2012 Mid-Flood tide
3 Nov 2012 Mid-Ebb tide
5 Nov 2012 Mid-Flood tide
6 Nov 2012 Mid-Ebb tide
5.4.3.
Due
to the lighting system for the access to C3 was off on 19 Nov 2012 during ebb
tide, the sample for C3 was taken in the alternative location under contingency
plan
5.4.4.
Due
to the blockage of road access to C5e and C5w on 17 Nov 2012 during mid flood
and mid-ebb tide, the sample was taken under contingency plan and the result
was presented in C5e WQM result on 17 Nov 2012 during mid-flood and mid-ebb
5.4.5.
WDII/RSS
advised that the dredging works for submarine pipeline at
5.4.6.
Based
on the joint inspection on 4 Jan 2012 for the NPR area, the 4-week water
quality monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9 to confirm no water
deterioration with respect to NPR was commenced since 7 Jan 2012 and it was
completed on 6 February 2012.
5.4.7.
Water
quality monitoring at WSD10 and WSD15 was temporary suspended while water
quality monitoring at WSD9 and WSD17 was implemented with respect to HK/2009/02
from 8 Feb 12 onwards;
5.4.8.
Water
quality monitoring at C8 and C9 have been implemented with respect to
HY/2009/19 since the marine bore piling work started on 28 Jan 12.
5.4.9.
Based
on the safety concern when external façade refurbishment was conducted by
contractor employed by Provident Centre (C9) since 3 Feb 2012, there is a fine
adjustment of the sampling location of water quality monitoring at C9 to the
closest accessible point prior to the completion of the external façade
refurbishment work.
5.4.10. With respect to the trial dredging at WCR2 was scheduled on
20, 22, 24, 25 March and 1, 3 ,
11, 13, 15, 17, 19, 20 Apr
and 3 May 2012, on-going water quality monitoring results at WSD21
during this period was checked and indicated that there was no contribution due
to the trial dredging operation. Enhanced review of water quality around
WCR2 was also implemented and no deterioration in the water quality was
observed.
5.4.11. Due to the access of water monitoring station at WSD19 was blocked
by LCSD construction works from 3 April 2012 to 2 May 2012 and lead to the
inaccessibility of sampling either land and marine, there is a fine adjustment
of the sampling point of WSD 19 since 5 April 2012 to the closest accessible
point prior to the completion of the construction activities.
5.4.12. Due to the dredging works for Cross Harbour Water Mains from
Wan Chai to Tsim Sha Tsui- DP6 was completed on 26 March 2012, the temporary
suspension of impact water quality monitoring at WSD7 and WSD20 after 27 April
2012 for the water quality monitoring at WSD7 and WSD20 have been monitored for
4-week period after the completion of DP6 to confirm no water deterioration.
Contract no. HK/2009/01 - Wan Chai Development
Phase II ¡V Central ¡VWanchai Bypass at HKCEC
5.4.13.
Water monitoring for Contract no. HK/2009/01 was
commenced on 23 July 2010. The proposed division of water monitoring stations
are summarized in Table 5.12 below.
5.4.14. Based on the safety concern when
the lighting system for the access to C3 was off, the water quality monitoring
were cancelled in the following dates and tides:
3 Nov 2012 During flood tide and ebb tide
5 Nov 2012 During flood tide
6 Nov 2012 During ebb tide
Table 5.12 Water
Monitoring Stations for Contract no. HK/2009/01
Station Ref. |
Location |
Easting |
Northing |
WSD Salt Water Intake |
|||
WSD7 |
|
834150.0 |
818300.3 |
WSD19 |
Sheung Wan |
833415.0 |
816771.0 |
WSD20 |
|
830750.6 |
816030.3 |
Cooling Water Intake |
|||
C1 |
HKCEC Extension |
835885.6 |
816223.0 |
C2 |
Telecom House |
835647.9 |
815864.4 |
C3 |
HKCEC Phase I |
835836.2 |
815910.0 |
C4e |
Great Eagle Centre |
835932.8 |
815888.2 |
C4w |
Wan |
835629.8 |
815889.2 |
Remarks:
- The water
monitoring stations for the dredging works under Contract No. HK/2009/01 should
also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at these
locations have not been carried out by others. Similarly, the water monitoring
stations for the dredging works under Contract No. HK/2009/02 should also
include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations have not been carried out by others.
- WSD7 and WSD20 water
quality monitoring were temporarily suspended since 27 Apr 2012.
Contract no. HK/2009/02 - Wan Chai Development Wan
Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
5.4.15.
Water monitoring for Contract no. HK/2009/02 was
commenced on 8 July 2010. The proposed division of water monitoring stations
are summarized in Table 5.13 below.
5.4.16.
Due to the blockage of road access to C5e and C5w
on 17 Nov 2012 during mid flood and mid-ebb tide, the sample was taken under
contingency plan and the result was presented in C5e WQM result on 17 Nov 2012
during mid-flood and mid-ebb.
Table 5.13 Water
Monitoring Stations for Contract no. HK/2009/02
Station Ref. |
Location |
Easting |
Northing |
|||
WSD Salt Water Intake |
||||||
WSD21 |
Wan Chai |
836220.8 |
815940.1 |
|||
WSD9 |
Tai Wan |
837921.0 |
818330.0 |
|||
WSD17 |
|
839790.3 |
817032.2 |
|||
Cooling Water Intake |
||||||
C5e |
Sun Hung Kai Centre (Eastern) |
836250.1 |
815932.2 |
|||
C5w |
Sun Hung Kai Centre (Western) |
836248.1 |
815933.2 |
|||
Remarks:
-
The water
monitoring stations for the dredging works under Contract No. HK/2009/01 should
also include WSD9, WSD17, WSD 21 and C5 if water quality monitoring at these
locations have not been carried out by others. Similarly, the water monitoring
stations for the dredging works under Contract No. HK/2009/02 should also
include WSD7, WSD9, WSD17, WSD 19, C1, C2, C3 and C4 if water quality
monitoring at these locations has not been carried out by others.
-
Water quality
monitoring at WSD9 and WSD 17 was implemented with respect to HK/2009/02 from 8
Feb 2012.
Contract
no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over
MTR Tsuen Wan Line
5.4.17.
Water monitoring for Contract no. HK/2010/06 was
commenced on 8 March 2011. The proposed division of water monitoring stations
are summarized in Table 5.14 below.
Table 5.14 Water
Monitoring Stations for Contract no. HK/2010/06
Station Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C2 |
Telecom House |
835647.9 |
815864.4 |
Contract no.
HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
5.4.18.
As
the removal of reclamation work of TS1 at CBTS has been completed, all
procedures have been rectified and complied with the conditions set in
EP-356/2009 and FEP-04/356/2009.
5.4.19.
Due to the commencement of the maintenance dredging
on 10 November 2010, water quality monitoring for Contract no. HY/2009/15 was
commenced on 9 November 2010. The proposed division of water monitoring
stations are summarized in Table 5.15 below.
Table 5.15 Water
Monitoring Stations for Contract no. HY/2009/15
Station Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C6 |
Excelsior Hotel |
837009.6 |
815999.3 |
C7 |
|
837193.7 |
816150.0 |
Remarks: - The cessation of seawater intake operation
for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then
terminated since 17 May 2011.
Contract no. HY/2009/19 ¡V Central- Wan Chai Bypass
Tunnel (North Point Section) and Island Eastern Corridor Link
5.4.20.
Due to the commencement of the marine bored piling
on 28 Jan 2012, water quality monitoring for Contract no. HY/2009/19 was
commenced on 28 Jan 2012. The proposed division of water monitoring stations
are summarized in Table 5.16 below.
Table 5.16 Water
Monitoring Stations for Contract no. HY/2009/19
Station Ref. |
Location |
Easting |
Northing |
Cooling Water Intake |
|||
C8 |
|
837970.6 |
816957.3 |
C9 |
Provident
Garden |
838355.0 |
817116.6 |
Remarks: C8 and C9 monitoring commenced on 28 Jan 2012.
5.4.21. Based on the safety concern when
external façade refurbishment was conducted by contractor employed by Provident
Center (C9) between 9 January 2012 to 30 July 2012 which caused to the
inaccessibility of sampling either land and marine since 3 Feb 2012, there is a
fine adjustment of the sampling location of water quality monitoring at C9
since 10 March 2012 to the closest accessible point prior to the completion of
the external façade refurbishment work.
5.4.22. Due to the access of water
monitoring station at WSD19 was blocked by LCSD construction works from 3 April
2012 to 2 May 2012 and lead to the inaccessibility of sampling either land and
marine, there is a fine adjustment of the sampling point of WSD 19 since 5
April 2012 to the closest accessible point prior to the completion of the
construction activities.
5.4.23. As per the meeting with the
representative of Excelsior Hotel and World Trade Centre on 17 May 2011, they
confirmed that the seawater intake for The Excelsior was no longer in use and
replaced by the connected permanent water supply from WSD pipelines since 11
January 2011. Thus, the impact water quality monitoring for the cooling intake
- C6 was terminated effective from 26 May 2011.
5.4.24. 24 hours monitoring of turbidity at the cooling water intakes
at C7 was conducted. With respect to the seawall collapsing
at TS4 on 17 November 2011, the 24 hours turbidity monitoring and was kept in
November 2011. Since the
reinstating the seawall was completed on 13 January 2012 and no any water deterioration
was performed, 24 hour turbidity monitoring was then suspended on 27 January
2012.
5.4.25.
Water monitoring results measured in this reporting
period are reviewed and summarized. Details of water quality monitoring results and
graphical presentation can be referred in Appendix 5.4.
Table
5.17 Summary of Water Quality
Monitoring Exceedances in Reporting Month
Contract no. |
Water Monitoring Station |
Mid-flood |
Mid-ebb |
|||||||||||
DO |
Turbidity |
SS |
DO |
Turbidity |
SS |
|||||||||
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|
LL |
|||
HK/2009/01 |
WSD19 |
0 |
0 |
2 |
1 |
0 |
1 |
0 |
0 |
3 |
2 |
0 |
1 |
|
|
C1 |
0 |
0 |
0 |
0 |
0 |
0
|
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C3 |
0 |
0 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C4e |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
C4w |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
|
Monitoring finished on 27 April
2012 |
WSD20 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
WSD7 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
||
HK/2009/01 &
HK/2010/06 |
C2 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HK/2009/02 |
C5e |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
0 |
1 |
0 |
|
|
C5w |
0 |
0 |
1 |
1 |
0 |
1 |
0 |
0 |
0 |
1 |
1 |
0 |
|
Monitoring started on 8 Feb 2012 |
WSD21 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
1 |
1 |
1 |
1 |
|
WSD9 |
0 |
0 |
1 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
||
|
WSD17 |
0 |
0 |
4 |
2 |
0 |
3 |
0 |
0 |
2 |
0 |
0 |
1 |
|
HY/2009/15 |
C7 |
1 |
0 |
0 |
1 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
HY/2009/19 Monitoring
started on 28 Jan 2012 |
C8 |
0 |
0 |
1 |
1 |
0 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
|
C9 |
0 |
0 |
3 |
4 |
2 |
0 |
0 |
0 |
1 |
1 |
0 |
0 |
||
Total |
3 |
0 |
12 |
10 |
3 |
6 |
0 |
0 |
9 |
6 |
4 |
3 |
||
Remarks: - The cessation of seawater intake operation for C6 was confirmed on 17 May 2011, the water monitoring at C6 was then terminated since 17 May 2011.
- WSD9 and WSD17 were implemented with respect to HK/2009/02 from 8 Feb 2012.
-
4-week water quality monitoring at WSD9, WSD10, WSD15, WSD17, C8, C9
were completed on 6 Feb 2012.
- C8 and C9 were implemented with
respect to HY/2009/19 from 28 Jan 2012.
- WSD7 and WSD20 were temporarily
suspended from 27 Apr 2012
5.4.26. Investigation found that no
exceedance was related to project works. The details of the recorded
exceedances can be referred to the Section 6.4.
5.4.27. Enhanced DO monitoring at 4
monitoring stations in Causeway Bay Typhoon Shelter and Ex-Public Cargo Works
Area was conducted three days per week during the reporting period. The action and
limit level exceedances of water quality monitoring are summarized in Table 5.18.
Table 5.18 Summary
of Enhanced Dissolved Oxygen Monitoring Exceedances in Reporting Month
Contract
no. |
Water
Monitoring Station |
Mid-flood |
Mid-ebb |
||
DO |
DO |
||||
|
LL |
|
LL |
||
HY/2009/15 |
C6 |
0 |
0 |
1 |
0 |
C7 |
0 |
1 |
1 |
0 |
|
Ex-WPCWA SW |
0 |
6 |
1 |
1 |
|
Ex-WPCWA SE |
4 |
5 |
5 |
3 |
|
Total |
4 |
12 |
8 |
4 |
5.4.28.
There were 12 action level exceedances and 16 limit
level exceedances recorded in enhanced dissolved oxygen monitoring in this
reporting period.
5.4.29. In response to the Condition 2.18
of the Environmental Permit no. EP-356/2009 requiring that a silt curtain /
impermeable barrier system be installed to channel water discharge flow from
Culvert L to locations outside the embayment area, a proposed replacement of the
requirement with additional dissolved oxygen monitoring has been conducted at
three monitoring stations, namely A, B and C between the eastern seawall of
Central Reclamation Phase III and the HKCEC Extension since November 2011 under
EP-356/2009 so that DO level between the eastern seawall of Central Reclamation
Phase II and the HKCEC extension could be continuously monitored. Details of additional DO monitoring results can be
referred in Appendix
5.4a.
Contract no. HK/2009/01 - Wan Chai Development Phase II ¡V Central
¡VWanchai Bypass at HKCEC
5.5.1.
No Inert C&D waste was disposed and non- inert
C&D waste was disposed of in this reporting month. Details of the waste
flow table are summarized in Table 5.19.
Table 5.19 Details of Waste Disposal for Contract no. HK/2009/01
Waste
Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
0 |
22245.415 |
TKO137, TM38 |
Inert
C&D materials recycled, m3 |
0 |
5104.5 |
N/A |
Non-inert
C&D materials disposed, m3 |
42.38 |
1092.08 |
|
Non-inert
C&D materials recycled, kg |
0 |
151143 |
N/A |
Chemical
waste disposed, kg |
200 |
8250 |
N/A |
*Marine
Sediment (Type 1 ¡V Open Sea Disposal), m3 |
0 (Bulk Volume) |
91164.2 (Bulk Volume) |
South of Cheung Chau |
* Marine
Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites)
& Type 2 ¡V Confined Marine Disposal) , m3 |
0 (Bulk Volume) |
43785 (Bulk Volume) |
East of Cha Chau |
Dredged Sediment Requiring Type 3 ¡V Special Treatment / Disposal
contained in Geosynthetic Containers |
0 (Bulk Volume) |
6773 (Bulk Volume) |
East of Cha Chau |
5.5.2.
There were no marine sediments Type 1 ¡V Open Sea Disposal
(Dedicate Sites) & Type 2 ¡V Confined Marine Disposal disposed in the reporting month.
Contract no. HK/2009/02 - Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass at WanChai East
5.5.3.
Inert and non- inert C&D waste were disposed of
in this reporting month. Details of the waste flow table are summarized in Table
5.20.
Table
5.20 Details of
Waste Disposal for Contract no. HK/2009/02
Waste
Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
5677.63 |
219417.03 |
TKO137 / TM 38 |
Inert
C&D materials recycled, m3 |
0 |
18161 |
N/A |
Non-inert
C&D materials disposed, m3 |
48.37 |
697.37 |
SENT Landfill |
Non-inert
C&D materials recycled, m3 |
N/A |
N/A |
N/A |
Chemical
waste disposed, kg |
700 |
6221 |
N/A |
Marine
Sediment (Type 1 ¡V Open Sea Disposal), m3 |
0 |
154,827 (Bulk volume) |
South of Cheung Chau |
Marine
Sediment (Type 1 ¡V Open Sea Disposal
(Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) , m3 |
782 |
115246 (Bulk volume) |
East of Sha Chau |
Marine Sediment (Type 1 ¡V Open Sea Disposal
(Dedicate Sites) & Type 2 ¡V Confined Marine Disposal) was disposed of in
this reporting month.
Contract no. HY/2009/15 - Central-Wanchai Bypass ¡V Tunnel (
5.5.4.
No Inert C&D waste and non- inert C&D waste
was disposed of in this reporting month. Details of the waste flow table are
summarized in Table 5.21
Table 5.21 Details of Waste Disposal for Contract no. HY/2009/15
Waste
Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
NIL |
141579.2 |
Tuen Mun Area 38 |
NIL |
65216 |
TKO137 FB |
|
Inert
C&D materials recycled, m3 |
NIL |
304 |
ex-PCWA |
NIL |
111.9 |
TS4 |
|
Non-inert
C&D materials disposed, m3 |
NIL |
252.2 |
SENT Landfill |
Non-inert
C&D materials recycled, kg |
NIL |
299361.5 |
N/A |
Chemical
waste disposed, kg |
NIL |
8,200 |
N/A |
Marine
Sediment (Type 1 ¡V Open Sea Disposal), m3 |
NIL |
97,857 (Bulk Volume) |
South of Cheung Chau |
Marine
Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined
Marine Disposal) , m3 |
NIL |
207,285 (Bulk Volume) |
East of Sha Chau |
Marine Sediment (Type 3 ¡V Special Treatment / Disposal
contained in Geosynthetic Containers) |
NIL |
7,050 (Bulk Volume) |
East of Sha Chau |
No Marine sediment (Type 1 ¡V Open
Sea Disposal) was disposed of in this reporting month.
Contract no. HK/2010/06 - Wan Chai Development Phase II ¡V Central ¡V Wan
Chai Bypass over MTR Tsuen Wan Line
5.5.5.
Non-inert C&D waste was disposed and Inert
C&D waste was recycled in this reporting month. Details of the waste flow
table are summarized in Table 5.22.
Table 5.22 Details of Waste Disposal for Contract no. HK/2010/06
Waste
Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
0 |
11366.23 |
TM38 |
Inert
C&D materials recycled, m3 |
36.3 |
348.1 |
N/A |
Non-inert
C&D materials disposed, m3 |
18.96 |
21.35 |
N/A |
Non-inert
C&D materials recycled, kg |
0 |
1374.5 |
N/A |
Chemical
waste disposed, L |
0 |
600 |
N/A |
Marine
Sediment (Type 1 ¡V Open Sea Disposal), m3 |
0 (Bulk Volume) |
3,694 (Bulk Volume) |
South Cheung Chau |
Marine
Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined
Marine Disposal) , m3 |
0 (Bulk Volume) |
12,297 (Bulk Volume) |
|
There were no marine sediments Type 1 ¡V Open Sea Disposal (Dedicate Sites) &
Type 2 ¡V Confined Marine Disposal dredging from bore-piling casing in the
reporting month.
Contract no. HY/2009/19 ¡VCentral- WanChai Bypass Tunnel (North Point
Section) and Island Eastern Corridor Link
5.5.6.
Inert and non-inert C&D waste were disposed of
and recycled in this reporting month. Details of the waste flow table are
summarized in Table 5.23.
Table 5.23 Details of Waste Disposal for Contract no. HY/2009/19
Waste
Type |
Quantity this month |
Cumulative Quantity-to-Date |
Disposal / Dumping Grounds |
Inert
C&D materials disposed, m3 |
17872.18 |
93591.24 |
TM38 |
Inert
C&D materials recycled, m3 |
195 |
1323 |
N/A |
Non-inert
C&D materials disposed, m3 |
39.32 |
151.53 |
N/A |
Non-inert
C&D materials recycled, kg |
6.58 |
111.22 |
N/A |
Chemical
waste disposed, L |
NIL |
0.29 |
N/A |
Marine
Sediment (Type 1 ¡V Open Sea Disposal), m3 |
0 |
83 |
South Cheung Chau |
Marine
Sediment (Type 1 ¡V Open Sea Disposal (Dedicate Sites) & Type 2 ¡V Confined
Marine Disposal) , m3 |
0 |
482 |
|
There was no marine
sediments Type1- Open Sea Disposal and Type 1 ¡V Open Sea Disposal
(Dedicate Sites) & Type 2 ¡V Confined Marine Disposal dredging from bore-piling casing in the reporting month.
6.0.1.
The Event Action Plan for construction noise, air
quality and water quality are presented in Appendix 6.1.
Contract
no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at
HKCEC
6.1.1
No exceedance was recorded in the reporting month.
Contract no. HK/2009/02 -
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
6.1.2
No exceedance was recorded in the reporting month.
Contract no. HY/2009/15 -
Central-Wanchai Bypass ¡V Tunnel (
6.1.3
No exceedance was recorded in the reporting month.
Contract no. HK/2010/06 -
Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line
6.1.4
No exceedance was recorded in the reporting month.
Contract
no. HY/2009/19 ¡V Central ¡V Wanchai Bypass Tunnel (North Point Section) and
Island Eastern Corridor Link under FEP-07/364/2009/A
6.1.5
Two limit level exceedances were recorded at M6 ¡V
HK Baptist Church Henrietta Secondary School on 1 and 6 November 2012 in the
reporting month. Investigations found that
major traffic noise was contributed in the noise monitoring and not related to the Project.
6.2.1
No exceedance was recorded in this reporting month
6.3.1.
No exceedance was recorded in 1-hr TSP and 24-hrs
TSP monitoring in the reporting month.
Contract
no. HK/2009/01 - Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass at
HKCEC
6.4.1
There were occasionally DOand SS exceedances
recorded at C3, C4e and C4w in this reporting month. Confirmed with Contractor,
trimming work on CHWM was conducted during the water quality monitoring. In
view that the water quality at monitoring stations located nearest the marine
work site well below the Action level and the silt screen was in proper
condition, the exceedances were considered not project related.
6.4.2
Turbidity and SS exceedances at WSD19 were
occasionally recorded in this reporting month. In view that the water quality
at monitoring stations located nearest the marine work site were well below
Action Level and the silt screen was in proper condition, the exceedances were
possible in relation to the changes of
water quality in the vicinity of the water quality monitoring station and not
project related.
Contract no. HK/2009/02 -
Wan Chai Development Phase II ¡V Central ¡V Wan Chai Bypass at WanChai East
6.4.3
There were turbidity and SS exceedances recorded at
C5w on 29 Oct 2012 during flood tide. Checking with Contractor¡¦s work, no
marine work was conducted during monitoring. Checking with contractor's
inspection record, the silt screen and silt curtain were in proper condition on
that day. The exceedance was possible in relation to the trapping of unknown
particles inside the silt screen. Contractor was reminded the water quality
near to the intake should be provided with sufficient protection. The
exceedance was not related to project works.
6.4.4
There was turbidity exceedance recorded at C5w on 31
Oct 2012 during flood tide. Checking with Contractor¡¦s work, no filling was
conducted on that day. Checking with contractor's inspection record, cleaning
screen panel at SHK intake was conducted during monitoring. The exceedance was possibly due to the
cleaning of screen panels at the SHK intake. Materials from cleaning of screen
panels was unavoidably collected during monitoring. The exceedance was
considered not project related
6.4.5
There were turbidity and SS exceedances recorded at
C5w and C5e on 31 October 2012 during ebb tide. Checking with Contractor¡¦s
records, diver inspection at SHK¡¦s well was conducted at 1300. Checking with
the Contractor and RSS daily records, the silt screen and silt curtain were in
proper condition. The exceedance was possible in relation to the disturbance of
sediment during diver inspection inside the SHK¡¦s well. The exceedances were
considered not work related.
6.4.6
There was SS exceedance recorded at C5e on 17 Nov
2012 during ebb tide. Checking with Contractor¡¦s work, no marine work was
conducted on that day. Checking with contractor's inspection record, the silt
screen was in proper condition on that day. The exceedance was possibly
relation to the natural variation or changes of water quality in the vicinity
of the water quality monitoring station. The exceedance was considered not
project related.
6.4.7
There were occasionally DO, turbidity and SS exceedances
recorded at WSD21 on 8 and 17 November 2012 during ebb tide. Confirmed with
Contractor, there was no work conducted during the water quality monitoring.
The exceedance was considered as natural variation or changes of water quality
in the vicinity of the water quality monitoring station and not project
related.
6.4.8
There were occasionally turbidity and SS exceedances
recorded at WSD17 and WSD9 in this reporting month. In view that the water
quality at monitoring stations located nearest the marine work site were well
below Action Level and the silt screen was in proper condition, the exceedance
was possible in relation to the natural variation or changes of water quality
in the vicinity of the water quality monitoring station and not project
related.
Contract no. HY/2009/15 -
Central-Wanchai Bypass ¡V Tunnel (
6.4.9
There were turbidity and DO exceedances recorded at C7 during mid-flood on
17 and 22 November 2012 respectively in this reporting month. After checking
with the Contractor¡¦s works, the deployed silt curtain was in proper condition
for TS2 seawall construction and reclamation. The exceedances were possible in
relation to the
natural variation or changes of water quality in the vicinity of the water
quality monitoring station and not project related.
6.4.10 There were
occasionally DO exceedances at Ex-WPCWA SE and Ex-WPCWA SW recorded in this
reporting month. No odour nuisance was noted during DO monitoring. After
checking with Contractor, there was no marine work undertaken at ex-WPCWA. The
exceedances were possible in relation to the accumulation of organic particles
discharge from culvert near monitoring station and considered not related to the Projects works.
Contract no. HK/2010/06 -
Wan Chai Development Phase II ¡V Central ¡VWanchai Bypass over MTR Tsuen Wan Line
6.4.11 No
exceedance was recorded in this reporting month.
Contract no. HY/2009/19-
Central- Wan Chai Bypass Tunnel (North Point Section) and Island Eastern
Corridor Link
6.4.12 There were
occasionally turbidity and SS exceedances at C8 and C9 recorded in this
reporting month. Confirmed with Contractor, there was no marine work conducted
near C8 and C9.The exceedances were possible in relation to the accumulation of
particles discharged from outfalls near monitoring stations and not related to
project.
6.4.13 Summary
for notification of exceedances can be referred to Appendix 6.2.
6.5.1
There was no non-compliance from the site audits in
the reporting month. The observations and recommendations made in each
individual site audit session were presented in Section 8.
6.6.1
There was no particular action taken since no
project-related non-compliance was recorded from the site audits and
environmental monitoring in the reporting month.
7.0.1.
According to Condition 3.4 of the EP-356/2009, this
section addresses the relevant cumulative construction impact due to the
concurrent activities of the current projects including the Central Reclamation
Phase III, Central-Wanchai Bypass and Island Eastern Corridor Link projects.
7.0.2.
According to the Monthly EM&A report (October
2012) of Central Reclamation Phase III (CRIII), filling works, building
construction works and pipe works were performed in the November 2012 reporting
month. The water quality monitoring was completed in October 2011 and no project-related
exceedance was recorded for air and noise monitoring. It can be concluded that
cumulative construction impact due to the concurrent activities of the current
projects with the Central Reclamation Phase III (CRIII) was insignificant.
7.0.3.
According to the construction programme of Wan Chai
Development Phase II, Central-Wan Chai Bypass and Island Eastern Corridor Link
projects, the major construction activities at Reclamation Shoreline Sub-zones
under Wan Chai Development Phase II were the filling at HKCEC3w, dredging at
submarine sewage pipelines, reinstatement of seawall block construction at
TCBR1W and marine bored piling at MTR Tunnel Crossing in the reporting month.
The major environmental impact was water quality impact at,
8.0.1.
During this reporting month, weekly environmental
site audits were conducted for Contracts no. HK/2009/01, HK/2009/02, HY/2009/15,
HK/2010/06 and HY/2009/19. No non-conformance was identified during the site
audits.
8.0.2.
Four site inspections for Contract no. HK/2009/01 was
carried out on 31 October 2012, 7, 14 and 22 November 2012 in reporting month.
Results of these inspections and outcomes are summarized in Table 8.1.
Table
8.1 Summary of
Environmental Inspections for Contract no. HK/2009/01
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
121031_01 |
31-Oct-12 |
The oil leakage was
observed at several locations which should be removed as chemical waste the
source of leakage should be identified. ( |
The oil stain was
removed |
Completion as observed
on 7-Nov-12 |
121107_01 |
7-Nov-12 |
The oil leakage was
observed on the platform of Leader 2 which should be removed as chemical
waste (Leader 2 Dredger) |
The oil stain was
removed |
Completion as observed
on 14-Nov-12 |
121114_01 |
14-Nov-12 |
The muddy water
dispersion out of the silt curtain was observed during filling. Gaps between
silt curtain should be prevented before filling operation ( |
The silt curtain
condition was improved. |
Completion as observed
on 22-Nov-12 |
121114_02 |
14-Nov-12 |
The oil stain was
observed on ground which should be removed and disposed as chemical waste
(Playground Area) |
The oil stain was
removed |
Completion as observed
on 22-Nov-12 |
121122_01 |
22-Nov-12 |
The oil stain was
observed on grounf which should be removed and disposed as chemical waste
(VIP area) |
The oil stain was
removed |
Completion as observed
on 28-Nov-12 |
121122_02 |
22-Nov-12 |
The C&D materials
around tree should be removed. (Playground Area) |
The C&D materials near
to tree was removed. |
Completion as observed
on 28-Nov-12 |
8.0.3.
Four site inspections for Contract no. HK/2009/02 was
carried out on 1, 8, 16 and 23 November 2012 during this reporting period. The
results of these inspections and outcomes are summarized in Table 8.2.
Table
8.2 Summary of
Environmental Inspections for Contract no. HK/2009/02
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
121101_01 |
1-Nov-12 |
The oil stain was
observed on the ground which should be removed as chemical waste |
The oil stain was
removed. |
Completion as observed
on 8-Nov-12 |
121101_02 |
1-Nov-12 |
The silt accumulated in
U-channel should be removed. (WCR2) |
The silt was removed. |
Completion as observed
on 8-Nov-12 |
121115_02 |
15-Nov-12 |
The stockpile should be
covered by tarpaulin sheet ( |
The stockpile is
covered. |
Completion as observed
on 23-Nov-12 |
121123_01 |
23-Nov-12 |
The maintenance of
wheel washing facility should be improved to ensure its efficiency. (Gate 2) |
The condition of wheel
washing facility has been improved. |
Completion as observed
on 29-Nov-12 |
8.0.4.
Five site inspections for Contract no. HY/2009/15 was
carried out on 30 October 2012, 6, 14, 20 and 27 November 2012 in reporting
month. The results of these inspections and outcomes are summarized in Table
8.3.
Table
8.3 Summary of
Environmental Inspections for Contract no. HY/2009/15
Date |
Observations |
Action taken by Contractor |
Outcome |
|
121030_01 |
30-Oct-12 |
Drip trays should be provided for Chemical drums (TS1,TS4,Ex-PCWA) |
Drip trays were provided |
Completion as observed on 6-Nov-12 |
121120_01 |
20-Nov-12 |
Filling materials should be avoid resting at the edge of
seawall block to prevent overflow (TZ1) |
Filling materials had been removed from the
edge of seawall block |
Completion as observed on 27-Nov-12 |
121120_02 |
20-Nov-12 |
Impermeable barrier behind filling works should be
tightened to avoid gaps (TS2) |
Silt curtain was deployed. |
Completion as observed on 27 Nov-12 |
121127_01 |
27-Nov-12 |
The oil stain was observed on ground which should be cleaned
and removed as chemical waste (TS4) |
The oil stain was removed |
Completion as observed on 5 Dec12 |
8.0.5.
Five site inspections for Contract no. HK/2010/06
was carried out on 29 October 2012, 5, 12, 22 and 26 November 2012 in reporting
month. The results of these inspections and outcomes are summarized in Table 8.4.
Table 8.4 Summary
of Environmental Inspections for Contract no. HK/2010/06
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
121112_01 |
12-Nov-12 |
Watering within site area should
be provided more regularly. (Section 2) |
Watering was observed. |
Completion as observed on
22-Nov-12 |
121112_02 |
12-Nov-12 |
The grouting materials on ground
should be tidied up and disposed as inert waste(2e) |
The grouting materials on ground
are tidied up. |
Completion as observed on
22-Nov-12 |
121122_01 |
22-Nov-12 |
The oil stain was observed on the
platform which should be removed and disposed as chemical waste (2w) |
The oil stain was removed. |
Completion as observed on
26-Nov-12 |
8.0.6.
Four site inspections for Contract no. HY/2009/19 was
carried out on 31 October 2012, 7, 15 and 21 November 2012 in reporting month.
The results of these inspections and outcomes are summarized in Table 8.5.
Table
8.5 Summary of Environmental
Inspections for Contract no. HY/2009/19
Item |
Date |
Observations |
Action taken by Contractor |
Outcome |
121107_01 |
7-Nov-12 |
Protection should be provided for
public gully before road surface breaking works |
Protection was provided |
Completion as observed on
15-Nov-12 |
9.0.1.
There was no complaint received in this reporting month.
9.0.2.
The details of cumulative complaint log and updated
summary of complaints are presented in Appendix
9.1.
9.0.3.
Cumulative statistic on complaints and successful
prosecutions are summarized in Table 9.1 and Table 9.2
respectively.
Table
9.1 Cumulative Statistics on Complaints
Reporting Period |
No. of Complaints |
Commencement works (Mar 2010) to last
reporting month |
27 |
November 2012 |
0 |
Project-to-Date |
27 |
Table
9.2 Cumulative Statistics on Successful
Prosecutions
Environmental Parameters |
Cumulative No. Brought Forward |
No. of Successful Prosecutions this month (Offence Date) |
Cumulative No. Project-to-Date |
Air |
- |
0 |
0 |
Noise |
- |
0 |
0 |
Water |
- |
0 |
0 |
Waste |
- |
0 |
0 |
Total |
- |
0 |
0 |
10.0.1. The
EM&A programme was carried out in accordance with the EM&A Manual
requirements, minor alterations to the programme proposed were made in response
to changing circumstances.
10.0.2.
WDII/RSS
advised that the dredging works for submarine pipeline at
10.0.3.
As
the land-based piling and filling works- DP3 at Tin Hau had been completed on 3
September 2012 and confirmed by RSS, the real-time noise monitoring results at FEHD
Hong Kong Transport Section Whitfield Depot was excluded under EP-356/2009
since 28 November 2012.
10.0.4.
The real-time noise monitoring at RTN2-Oil Street Community Liaison
Centre has been relocated to City Garden Electric Centre (RTN2a- Electric
Centre) on 5 Oct 2012, which is a representative of noise sensitive
10.0.5.
Water
quality monitoring at WSD10 and WSD15 will be temporary suspended while water
quality monitoring at WSD9 and WSD17 were implemented with respect to
HK/2009/02 for the water quality monitoring scheduled on 8 Feb 12 onwards;
10.0.6.
Water
quality monitoring at C8 and C9 have been implemented with respect to
HY/2009/19 since the marine bore
piling work started on 28 January 2012.
10.0.7.
Based
on the safety concern when external façade refurbishment was conducted by
contractor employed by Provident Centre (C9) between 9 January 2012 to 30 July
2012 which caused to the inaccessibility of sampling either land and marine
since 3 Feb 2012, there is a fine adjustment of the sampling location of water
quality monitoring at C9 since 10 March 2012 to the closest accessible point
prior to the completion of the external façade refurbishment work.
10.0.8.
Due
to the access of water monitoring station at WSD19 was blocked by LCSD
construction works from 3 April 2012 to 2 May 2012 and lead to the
inaccessibility of sampling either land and marine, there is a fine adjustment
of the sampling point of WSD 19 since 5 April 2012 to the closest accessible
point prior to the completion of the construction activities.
10.0.9.
With respect to the trial
dredging at WCR2 was scheduled on 20, 22, 24, 25 March and 1, 3, 11, 13, 15, 17, 19, 20 Apr
and 3 May 2012, on-going water quality monitoring
results at WSD21 during this period was checked and indicated that there was no
contribution due to the trial dredging operation. Enhanced review of
water quality around WCR2 was also implemented and no deterioration in the
water quality was observed.
10.0.10. Due to the dredging works for Cross Harbour Water Mains from
Wan Chai to Tsim Sha Tsui- DP6 was completed on 26 March 2012, the temporary
suspension of impact water quality monitoring at WSD7 and WSD20 after 27 April
2012 for the water quality monitoring at WSD7 and WSD20 have been monitored for
4-week period after the completion of DP6 to confirm no water deterioration.
10.0.11. The
scheduled construction activities and the recommended mitigation measures for
the coming month are listed in Table 10.1.
Table 10.1 Construction
Activities and Recommended Mitigation Measures in
Coming Reporting Month
Contract
No. |
Key
Construction Works |
Recommended
Mitigation Measures |
HK/2009/01 |
Marine Works ¡P
Fabrication of precast concrete caisson seawalls, precast box culvert
(Bay 10) and precast discharge outfall in precasting yard at ¡P
Dredging works for Type 2 sediment underneath ¡P
Dredging works between CH290 and CH370 at east of HKCEC near Wan Chai
west ferry pier would be commenced after completion of removal of high spot
of Grade 75 rock fill along the submarine pipeline of cross-harbour
watermains. ¡P
Excavation work and tie back system for construction of pipe pile wall
near expo drive East ¡P
Removal of seawall and rock armour at ¡P
Rockfilling at east of HKCEC near ¡P
Trust block construction at TST landfall ¡P
Rockfilling and rock armour protection works to cross-harbour
watermains ¡P
Reinstatement works at TST seashore including removal of silt screen ¡P
Fresh water flushing, final cleaning and sterilizatioin for
cross-harbour watermains CHA, CHB, CHE & CHF ¡P
Installation of Impressed Current Cathodic Protection (ICCP) system to
CHA and CHB Fresh Watermains, Cooling
Watermains and Salt Watermains (On Land) ¡P
Works would be continued at Zone B1-5A, B2-1, B3-1, A1-1, A1-2, A2-2,
A1-4(CHWM), A2-3D, A3-2A, A3-4B, A3-3C, run-out of Renaissance Hotel and C1-6
¡P
Mainlaying works at Zone C1-6 ¡P
Reinstatement works at Zone B1-5A and B2-1 ¡P
Mainlaying works at Zone B3-1 ¡P
Mainlaying works at Convention Avenue in Zone A1-1 and A1-2 and the
next TTA workfront at Zone A1-2 (CHWM) would be commenced accordingly. ¡P
Mainlaying works and grouting works at jacking pit in Zone A1-2A &
A1-3A of Convention Avenue would be resumed upon completion of pressure test
for intake and discharge pipeline of SOC and HKAPA. ¡P
Mainlaying works at traffic island near junction between Convention
Avenue and Fenwick Pier Street would be continued. ¡P
Pipe laying works for Heading no. H1 would be continued .The remaining
pipe works at Zone A3-2A ¡P
Mainlaying works at Zone A3-4B would be continued and the works at
Zone A3-4A & A3-5A would be subsequently commenced concurrently after the
Zone A3-4B had been completed reinstated and reopened to public. ¡P
Pressure test for the 1 no. cooling watermains (AF) E&M Works ¡P
Electrical works in Cooling Water Pumping Stations P5 ¡P
Power supply to cooling water pumping station P5 from L.V. switchboard
¡P
Initial commissioning for Cooling Water Pumping Stations P5 ¡P
Power energization for Cooling Water Pumping Stations P5 ¡P
Full commissioning for Cooling Water Pumping Stations P3, P4 & P5 |
¡P
To conform the installation and setting as in the silt
screen deployment plan ¡P
Frequency spray water on the dry dusty road and on the
surface of concrete breaking ¡P
To cover the dusty material or stockpile by impervious
sheet ¡P
To space out noisy equipment
and position as far as possible from sensitive receiver. ¡P
To well maintain the mechanical
equipments / machineries to avoid abnormal noise nuisance. ¡P
Machines and plant that may be
in intermittent use should be shut down between work periods or should be
throttled down to a minimum ¡P
Daily visual inspection of silt screen and silt curtain to
ensure its operation properly |
HK/2009/02 |
¡P
Complete rectification works of cooling mains and pressure test. ¡P
Continue 800MS pipe installation inside Ex-pet Garden. ¡P
Continue entrance area works at WSD Pumping Station ¡P
Continue the finishing and E&M works of WSD Salt Water Pumping
Station. ¡P
Continue construction of Bay 1b ¡V 2 Salt water intake culverts at WCR1
area. ¡P
Complete salt water intake culverts Bay 10 ¡V 11 construction. ¡P
Continue salt water intake culvert at transition bays inside jacking
pit. ¡P
Continue remaining drainage works and reinstatement works along Wan
Shing Street. ¡P
Complete Outfall Pipe B connection inside outfall seaside cofferdam
and Dye Tests ¡P
Continue construction of 1800 connection of Box Culvert N1, Bay 4
& Bay 5 and FRP installation at
WCR1 area. ¡P
Commence concreting works for the Observation Deck Level at the New
Ferry Pier. ¡P
|
¡P
To cover the dusty material or stockpile by impervious
sheet; ¡P
Frequency spray water on the dry dusty road and on the
surface of concrete breaking ¡P
To well maintain the mechanical equipments / machineries
to avoid abnormal noise nuisance and dark smoke emission ¡P
To conform the installation and setting as in the silt
screen and silt curtain deployment plan ¡P
Movable noise barrier shall be
deployed for demolition works ¡P
Daily visual inspection of silt screen and silt curtain to
ensure its operation properly ¡P
Review silt screen deployment and
silt curtain deployment and resubmit associate plans to EPD ¡P
Implement silt screen and silt
curtain in accordance with the associated plans submitted to EPD. |
HY/2009/15 |
¡P
Formation of temporary seawall at TS2 ¡P
TZ1 and TS2 reclamation works |
¡P
Daily visual inspection of silt screen and silt curtain to
ensure its operation properly ¡P
Implement silt screen and silt
curtain in accordance with the associated plans submitted to EPD. |
HK/2010/06 |
¡P
Pile head breaking ¡P
Platform Disassembly ¡P
Dredging ¡P
Bored Pile cutting |
¡P
To conform the installation and setting as in the silt
screen and silt curtain deployment plan ¡P
To space out noisy equipment
and position as far as possible from sensitive receiver. ¡P
Daily visual inspection of silt screen and silt curtain to
ensure its operation properly |
HY/2009/19 |
¡P
Construction works for Box
Culvert T ¡P
Marine Piling ¡P
Construction of 1500f drainage pipe |
¡P
To conform the installation and setting as in the silt
screen and silt curtain deployment plan |